- All Routes
- Eastern: Anglia
- Eastern: East Coast
- Eastern: East Midlands
- Eastern: North & East
- North West & Central: Central
- North West & Central: North West
- North West & Central: West Coast Mainline South
- Southern: Kent
- Southern: Network Rail High Speed
- Southern: Sussex
- Southern: Wessex
- Wales & Western: Wales & Borders
- Wales & Western: Western
National & regional news

Railway line between East Grinstead and Lingfield to reopen by Monday 30 March
Work is underway to reopen the railway between East Grinstead and Lingfield by 30 March after two landslips blocked the line.

Network Rail begins work to improve three level crossings in Staffordshire
Network Rail will begin work to improve three level crossings in Staffordshire this week, which will make sure they can continue to be used reliably for years to come.

Wherry lines fully re-open following completion of 23 days of engineering works
The line between Norwich and Lowestoft re-opened today following the completion of track works in the Hassingham area to improve journey reliability for passengers.

Elected members visit Greenock bridge works
Engineers will shortly complete work on the £1million refurbishment of the railway bridge at Dellingburn Street in Greenock as part of a wider programme of maintenance on structures.

Vital repairs for storm-damaged Dumfries rail line now underway
Work to repair the landslip beneath the railway between Kilmarnock and Dumfries is now getting underway following damage sustained during Storm Ciara.

Saturday Extreme Weather Update: Abergavenny to Hereford Line Reopened
Network Rail has made additional progress in repairing the railway network across the Wales and Borders route following Storm Ciara, Storm Dennis and additional rainfall this week.

Extreme Weather Update: Major progress made by Network Rail. Passengers thanked
Network Rail has made substantial progress in repairing the railway network across the Wales and Borders route following Storm Ciara, Storm Dennis and additional rainfall this week.

Billericay Landslip - Normal service expected to resume on Monday 24 February
On the morning of Wednesday 19 February, a landslip caused damage to the tracks between Billericay and Wickford on the Southend Victoria line. Ballast, the stones that help keep tracks safely in place, had fallen away under a section of track.
Network Rail’s engineers are working to repair the damage to the tracks and the embankment. With the line already planned to close this weekend for overhead line upgrade work, we expect all repairs to be completed for normal service to resume on Monday 24 February.
Results 4745 - 4752 out of 14364