Excavation of new Crossrail dive-under begins at Acton: Acton excavation

Thursday 31 Oct 2013

Excavation of new Crossrail dive-under begins at Acton

Region & Route:
| Wales & Western: Western
| Wales & Western
| Southern

The excavation of 34,000 tonnes of earth for a new rail underpass just outside Acton Main Line station has begun as part of works to prepare the route for the full arrival of Crossrail services in 2019.

The dive-under is needed so that trains leaving the Acton freight yard do not delay passenger trains heading towards Acton Main Line and on to central London.

Currently freight trains enter and leave the freight yard by crossing the mainline passenger tracks. The new dive-under will allow the trains to access the yard without affecting passenger services, increasing capacity and reliability.

The start of excavation follows nearly two years of work to re-configure the freight yard. The work on the dive-under is being managed by Network Rail and is expected to last until 2016.

Matthew White, Crossrail’s surface director said: “The dive-under at Acton is a vital part of the Crossrail works in west London, helping to ensure a fast, frequent and reliable service for passengers when full services start in 2019.”

Rob McIntosh, Crossrail programme director, Network Rail, said: “The Acton dive-under is one of the most complex infrastructure structures we are delivering for Crossrail. The new dive-under will ensure the activities of this important freight yard, which services the London network, are secured when the Crossrail services begin. The team has worked closely with principal contractors BAM Nuttall to achieve this milestone and over the coming months we will really be able to see the dive-under structure emerge.”

Crossrail will transform public transport, making it quicker and easier for people to get to a range of destinations across London and the South East. Residents in west London and Berkshire will benefit from new trains, frequent services and better stations as part of the project.

Network Rail is responsible for the design, development and delivery of the parts of Crossrail that are on the existing network. The work includes upgrading 43 miles of track as well as improving 27 stations from Maidenhead in the west to Abbey Wood and Shenfield in the east.

Notes to editors

The Crossrail route will pass through 38 stations and run more than 100 km from Maidenhead and Heathrow in the west, through new twin-bore 21 km (13 miles) tunnels below central London to Shenfield and Abbey Wood in the east.

When Crossrail opens it will increase London's rail-based transport network capacity by 10%, supporting regeneration and cutting journey times across the city. Crossrail services are due to commence through central London in 2018.

Network Rail is a key partner in Crossrail. Network Rail is responsible for the design, development and delivery of the parts of Crossrail that are on the existing network. Its work will integrate Crossrail with the national rail network. The work includes upgrading 43 miles of track, improving 27 stations, and work on 20 bridges.

The exact opening strategy for Crossrail has not yet been finalised but the current planning assumption is that Crossrail services will be introduced as follows:

  • Heathrow to Paddington (mainline platforms) – May 2018 (when the Crossrail concession takes over the Heathrow Connect service)
  • Paddington (Crossrail platforms) to Abbey Wood – December 2018
  • Paddington (Crossrail platforms) to Shenfield – May 2019
  • Full through service (including services to Maidenhead) – December 2019

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - South East route
020 3357 7969
southeastroutecomms@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk