Work to build Leicestershire temporary footbridge begins as current bridge is transformed

Region & Route:
Eastern
| Eastern: East Midlands

Construction of a temporary bridge in Kibworth has begun whilst essential work to adapt the existing bridge takes place, paving the way for a fully electrified railway between Kettering and Wigston. 

School Road bridge will be demolished this Autumn, before being reconstructed to provide the clearance needed for overhead wires to pass underneath. 

The wires will eventually power electric and bi-mode trains through the East Midlands as part of the Midland Main Line upgrade. The multi-million-pound programme supports the Government’s ambitions for decarbonisation and will offer more reliable journeys for passengers. 

In the meantime, work to build a temporary footbridge is now underway and is set to be completed by autumn 2023. This will allow residents to access shops and local schools safely whilst work on the permanent bridge takes place.  

Network Rail has worked closely with Kibworth Parish Council, Harborough District Council and Leicestershire County Council whilst engaging with the local community. The temporary structure is being erected to allow for the work to be carried out with as little impact on the community as possible. 

The new, permanent bridge is due to be completed by spring 2024 and will help to create a cleaner, greener railway for passengers travelling along this section of the Midland Main Line in the future.  

Gavin Crook, Principal Programme Sponsor for Network Rail’s East Midlands Route, said: “I’m pleased that work is pushing forward to build a temporary bridge whilst the existing bridge at School Road is reconstructed, clearing space for overhead line equipment to be installed underneath. 

“We have listened carefully to Kibworth villagers, as well as the parish council, and have worked to agree a diversion route that best suits the needs of the community. The temporary bridge will make sure that those with pushchairs, wheelchairs and scooters can safely access local schools and nurseries in the village.  

“I’d like to thank the community for their feedback and support, and I look forward to the new bridge opening next year.” 

ENDS 

Notes to Editors

  • The temporary bridge will close during selected periods of work to demolish and reconstruct the permanent bridge. This is for the safety of engineers and members of the public. Local residents will be notified of exact dates and times of any closures closer to the time.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Joshua Chapman
Media Relations Manager
Network Rail
joshua.chapman@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk