VIDEO: time-lapse shows major repairs as railway through Telford reopens to passengers: Telford embankment complete aerial

Friday 29 Mar 2024

VIDEO: time-lapse shows major repairs as railway through Telford reopens to passengers

Region & Route:
North West & Central
| North West & Central: Central

The railway between Wolverhampton and Shrewsbury has fully reopened to passenger trains after engineers complete emergency repairs to a failed railway embankment.

Network Rail is thanking passengers for their patience this morning (Friday 29 March) after three weeks of disruption following a landslip between Oakengates and Wellington stations.

New time-lapse video footage has been released showing the scale of work by Network Rail and its contractor Murphy to rebuild the embankment so that trains can safely resume.

On Friday 8 March Network Rail closed the line near Oakengates station in both directions for safety reasons following a landslip on a steep railway embankment.

More than 5,000 tonnes of material slipped beneath a 50-metre section of the railway after persistent heavy rainfall over the winter months had weakened the earthwork beneath it.

Engineers have been working around the clock to shore up the landslip. Work to restabilise the railway embankment - which is approximately 15 metres in height - involved digging out material that’s slipped to create a new profile for the slope. Large ‘steps’ were cut into the slope before engineers backfilled it with over 16,000 tonnes of locally sourced stone, helping to reduce the gradient and strengthen the embankment.

Network Rail has worked closely with its train operator partners to keep passengers moving during the closure with an amended timetable and bus replacement services. A full timetable has resumed on the route this morning in time for people to travel over the Easter bank holiday weekend.

Adam Checkley, infrastructure director for Network Rail’s Central route, said: “I want to say a huge thanks to passengers and the local community who’ve been disrupted over the last three weeks while we completed emergency repairs after prolonged heavy rain caused a significant landslip in Telford.

“Our repairs have involved bringing over 16,000 tonnes of material from local quarries to shore up the Victorian-built embankment to make it safe for trains to resume in time for the Easter weekend.

“We’re pleased to say that this important route has reopened this morning and advise people travelling to check www.nationalrail.co.uk for journey information.”

Jonny Wiseman, West Midlands Railway customer experience director, said: “I’d like to thank customers for their patience as Network Rail has been carrying out essential works to fix the landslip and it’s good news that the railway can now reopen fully.

“I would urge passengers to continue to check their journeys ahead of travelling on Friday, as we move trains to their correct location to resume a normal service.”

Councillor Shaun Davies, Leader of Telford & Wrekin Council added, "We extend our heartfelt gratitude to Network Rail and its partners for their swift and dedicated response in restoring the railway line between Wolverhampton and Shrewsbury.

"Their tireless efforts not only ensured the timely repair of the embankment but also facilitated the provision of temporary bus services, allowing residents and passengers to seamlessly continue their journeys to and from Telford.

"We have been working hard to convene partners and coordinate efforts to minimise disruption, and this collaborative approach exemplifies our commitment to ensuring the safety and convenience of our community."

Passengers are being advised about major work taking place on the West Coast Main Line over the Easter bank holiday weekend: ‘Travel either side’ advice for West Coast Main Line passengers this Easter bank holiday (networkrailmediacentre.co.uk).

For the latest travel information please visit www.nationalrail.co.uk

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk