Transpennine Route Upgrade’s first electric wires now in place to power greener journeys: Transpennine Route Upgrade’s first electric wires now in place to power greener journeys

Thursday 1 Dec 2022

Transpennine Route Upgrade’s first electric wires now in place to power greener journeys

Region & Route:
Eastern
| Eastern: North & East

Over 30 miles of train-powering electric wires are now in place to help deliver cleaner, greener journeys in the future as part of the multi-billion-pound Transpennine Route Upgrade.

The work has taken place between Church Fenton and Colton Junction, where trains from Leeds join the East Coast Main Line into York. This is one of the busiest stretches of railway in the north, with over 100 trains using the line each day.

It is the first step towards a cleaner, greener, fully electrified railway between York, Leeds, Huddersfield and Manchester. When the newly-installed wires are energised, they will allow more environmentally-friendly electric and hybrid trains to run at speeds of up to 125mph – which is 30mph faster than they can currently run.

Rob McIntosh, Managing Director for Network Rail’s Eastern region said: “We’ve reached a major milestone on our journey to bring cleaner, greener trains to the north and deliver a better railway which people can rely on.

“Our teams in York and Manchester are working in tandem to electrify sections of the route and will eventually connect to unlock faster, more frequent services and help passengers get to where they need to be, on time.”

Rail Minister Huw Merriman said: “Our multi-billion pound Transpennine Route upgrade will transform journeys for passengers across the North of England, with faster, more frequent services and improved accessibility.

“This is the first major milestone on the way to a fully electrified route between York, Leeds, Huddersfield and Manchester, which will reduce journey times and save 87,000 tonnes of carbon emissions each year."

Over the last four months, Network Rail engineers have put in just under 9000 hours of work to install a total of 37 miles of overhead wire. Work was carried out overnight and at weekends to cause as little disruption to passengers as possible.

When complete across the full 70-mile route across the Pennines, rail passengers will be helping to save up to 87,000 tonnes of carbon emissions each year – equivalent to 5.9 million car journeys along the same route. For people living near the railway, it will also mean better air quality and quieter trains.

To maintain an equally eco-friendly construction, the new overhead line equipment was assembled locally at the Transpennine Route Upgrade’s own Joseph Lynn Logistics Hub near Sherburn-in-Elmet and transported to site by train.

ENDS

Notes to Editors

Work to join the newly installed wires into the existing overhead line equipment on the East Coast Main Line at Colton Junction will take place in the future, ahead of their energisation in 2024.

Engineers installed a total of 37 miles of overhead wire along just over six miles of a four-track stretch of line, together with an additional 9 miles of earth wires. 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Louise Leighton
Media Relations Manager
Network Rail
07858 375508
louise.leighton2@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk