Transformation of Southend rail service underway: Structure install weeknights June 2018

Monday 9 Jul 2018

Transformation of Southend rail service underway

Region & Route:
Eastern: Anglia
| Eastern

New trains, more services and fewer delays will transform the Southend Victoria branch line from 2020, as work is underway on a £46m upgrade to replace the overhead wiring system.

The existing wiring system, which was built in the 1950s and is the oldest in the country, is being replaced with a new system that will be more reliable, adapts to temperature and will mean fewer delays for passengers.

Network Rail’s Team Orange has so far installed 220 structures, which will carry the new wires, between Shenfield and Rayleigh. A further 166 structures have been installed between Rayleigh and Southend during weeknight shifts on Monday, Tuesday and Wednesdays. The remaining 144 structures will be replaced over the next year.

Between Shenfield and Wickford, nearly 12km of new overhead wire has been installed. A total of 128km will be installed along the whole line.

Southend Victoria project progression
Southend Victoria project progression

Once complete, the line will be much more reliable and enable more services to run.

Meliha Duymaz, Network Rail’s route managing director for Anglia, said: “We have made huge progress on our upgrade of the Southend Victoria branch line, which will improve reliability and meet future passenger demand as part of our Railway Upgrade Plan. When complete, this project and the introduction of the new trains will herald a complete transformation of the line from what it is today. We understand that the work affects journeys for those who are traveling late, and we thank passengers for their patience.”

Jamie Burles, Greater Anglia managing director, said: “We’re sorry that customers’ journeys are inconvenienced by this engineering work. However, this work is necessary for the modernisation of the railway in East Anglia, and will mean that our brand new trains, due to come into service from next year, will be able to run on a much more reliable set of overhead wires. By the end of 2020, when all of our new trains are in service, the Southend Victoria railway will have been transformed.”

More information about the project can be found at: www.networkrail.co.uk/anglia-ole-renewals

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Katie Mack
Media relations manager (Anglia route)
0330 8577 132
Katie.Mack@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk