Friday 31 Oct 2025
Train services resume between Bristol and Bath following track work through St Anne’s tunnel
- Region & Route:
- Wales & Western: Western
- | Wales & Western
Network Rail’s four-day track replacement between Bristol and Bath is complete. On Monday (27 October) engineers began work installing new rail, sleepers and stone through St Anne’s tunnel, working around the clock and finishing the job in the early hours of this morning (Friday 31 October), as planned.
At any one time up to 65 people were out on track to carry out the work which involved installation of over a kilometre of rail, 5,000 tonnes of stone and 1,565 sleepers.
Throughout the work buses replaced trains between Bristol Temple Meads and Bath Spa stations. Additional track maintenance and work was also carried out at other locations along the line.
Mark Parker, lead portfolio manager for Network Rail, said: “This work has been a vital piece of maintenance to ensure the continued safe and reliable running of train services on the busy mainline between Bristol and Bath.
“While we do our best to keep disruption to a minimum there is inevitably an impact on rail passengers and also potentially for residents. I’d therefore like to thank everyone for their patience while this work was completed.”
Oana Apetroaie, GWR station manager for Bath Spa and Chippenham, said: “We’re pleased that train services are now running again between Bath Spa and Bristol Temple Meads and thank customers for their patience.
“These track works help support the reliability of a key section of the railway for the region, helping people to travel sustainably.”
Contact information
      Passengers / community members
      Network Rail national helpline
      03457 11 41 41
    
      Latest travel advice
      Please visit National Rail Enquiries
    
      Journalists
      Emily Maiden
      
      Network Rail
      
      
      Emily.Maiden@networkrail.co.uk
    
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
            Follow us on Twitter: @networkrail
            Visit our online newsroom: www.networkrailmediacentre.co.uk
          
 
      