THREE MONTHS TO GO: Brighton Main Line investment will close railway between Three Bridges and Brighton/Lewes for nine days over February half-term: Thameslink train and track at Three Bridges station

Tuesday 10 Nov 2026

THREE MONTHS TO GO: Brighton Main Line investment will close railway between Three Bridges and Brighton/Lewes for nine days over February half-term

Region & Route:
Southern
| Southern: Sussex

Buses will replace trains as a significant investment on the Brighton Main Line over the February half-term will improve the reliability of the route into the future.

Network Rail and train operators are urging customers to plan ahead and check before they travel over the February half-term as major engineering work will close a section on the busy Brighton Main Line from Saturday 13 to Sunday 21 February 2027. 

The work forms part of a significant investment to improve the reliability and safety of this vital route, which is among the most complex and intensively used in the country. 

Engineers will complete a concentrated programme of track renewals, strengthening of earthworks, new conductor rail and level crossing and tunnel improvements. 

Key improvements include: 

  • Track renewal: New rails at Plumpton and Preston Park plus renewed track and switches and crossings at Keymer Junction near Wivelsfield to help cut delays and boost performance. 
  • Earthworks: Strengthening and stabilisation works at Haywards Heath cutting and the Balcombe Stamford rock cutting to reduce the risk of landslips and rock falls. 
  • Tunnels: Structural works at Balcombe Tunnel to ensure continued safe operation and install of new rails through the Clayton Tunnel. 
  • Electrical: New conductor rail between the Clayton Tunnel and Preston Park. The conductor rail, also known as the third rail, allows us to supply power to the trains. 
  • Level crossings: new signalling and renewal of the level crossings at Spatham Lane near Westmeston, and at Hamsey in East Sussex. 

Lucy McAuliffe, Network Rail’s Sussex route director, said: “The Brighton Main Line is one of the busiest rail corridors in the country, with complex and intensively used infrastructure. This work is vital to reduce faults, improve journey reliability and keep services running safely for years to come. 

“We know closing the railway is an inconvenience, but the extended closure over February half-term 2027 allows us to deliver a huge volume of work at once, avoiding repeated disruption across multiple weekends or during the busy summer season.” 

Jenny Saunders, Southern, Gatwick Express and Thameslink Customer Service Director said: “This major work over February half-term week is crucial to keeping services reliable for our Gatwick Express, Southern and Thameslink customers. We’ve been working on detailed plans to keep customers moving. Trains to and from Brighton will be diverted and buses will replace services on affected routes for nine days, so we’re asking customers to save the dates in their diaries. 

“By giving people advance notice, we’re encouraging everyone to think about their travel options over that week in February, especially as some may find it easier to plan to work flexibly where they can.” 

During the nine-day closure, rail replacement buses will run between Three Bridges and Brighton or Lewes via Haywards Heath and other intermediate stations.

There will also be a direct train service between London Victoria and Brighton, but it will be diverted to use an alternative route via Horsham and Littlehampton, extending journey times. Customers travelling between the Brighton and Hove areas and Gatwick Airport or London are encouraged to use this diverted train service rather than replacement buses. 

A major information campaign is now getting under way to provide customers with advance notice of the dates. Customers are being advised to plan ahead, and allow extra time for their journeys throughout the nine-day closure. More information about the work that is being carried out, the impact on journeys and  plans for keeping people moving during the work will be available on the Network Rail and train operators’ websites.  

Travel information 

Over the nine days, replacement buses will run on the following routes to help customers complete their journeys: 

  • Three Bridges via all stations to/from Brighton 
  • Three Bridges and Lewes via Haywards Heath and Cooksbridge 
  • Three Bridges and Haywards Heath  
  • Haywards Heath and Plumpton 
  • Lewes and East Grinstead (weekdays only)  

Train times across the East and West Coastway routes to and from Brighton will also be revised as a result of the closure of the main line. 

Notes to Editors

Online journey planners such as the National Rail Enquiries website will start showing the details and revised train and replacement bus times for the affected week in February later this month.  

As part of the ongoing investment into the Brighton Main Line, significant engineering work will also take place in the Redhill area over the Christmas 2026 and New Year 2027 period. 

More information on the engineering work in the Redhill area.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Paul Prentice
Communications Manager
07354 529345
paul.prentice@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk