Rail passengers urged to check before they travel this Christmas and New Year as major upgrades are planned: Great Eastern Mainline OLE renewals

Monday 10 Dec 2018

Rail passengers urged to check before they travel this Christmas and New Year as major upgrades are planned

Region & Route:
Eastern: Anglia
| Eastern

Passengers in Norfolk, Suffolk, Essex and East London are advised to check before they travel this Christmas and in 2019 as major railway upgrades are planned.

Over the Christmas period, Network Rail engineers will be carrying out the following upgrades to the network as part of the company’s Railway Upgrade Plan:

  • Installation of 12.5km overhead wire at Forest Gate on the Great Eastern Main Line as part of a £250m investment to improve reliability
  • Installation of structures that will carry new overhead wire on the Southend Victoria branch line as part of a £46m investment to reduce delays and cancellations especially in hot weather
  • Work on the Felixstowe branch line as part of the £60.4m project to install a new 1.4km loop near Trimley to increase freight traffic and improve reliability for passenger services
  • Works at Shenfield station as part of the Crossrail programme
  • While the line is closed, TfL will carry out bridge demolition work as part of the Ardleigh Green Bridge project near Romford

Passengers are advised to check before they travel as there will be changes to services between Ingatestone and London Liverpool Street on the main line and between Billericay on the Southend Victoria line. This will affect Greater Anglia and TfL Rail services from Sunday 23 December to Tuesday 1 January.

Further work will take place in early 2019 which will see the overhead wiring system upgraded on the final stretch between Forest Gate and London Liverpool Street. Passengers are advised to check before they travel.

Meliha Duymaz, Network Rail’s route managing director for Anglia, said: “We are making a huge investment into Anglia’s rail network to carry out major improvements to rail travel in the region as part of our Railway Upgrade Plan. This means that the line will be closed over the Christmas period to allow our engineers to carry out these important upgrades. I’d like to thank passengers for their patience while we carry out this work and advise them to check before they travel."

Jamie Burles, Greater Anglia Managing Director said: “We know customers would rather stay on the train all the way to their destination, but I’d like to assure passengers that they will still be able to complete their journeys over the festive season, even if part of it is by bus. We’re sorry that customers are inconvenienced by these works, but together with Network Rail, we’re working to transform the railway in East Anglia. Next year the first of our new trains that we’re getting to replace all of our existing trains will come into service.”

Passengers are advised to check before they travel at www.nationalrail.co.uk. A breakdown of how journeys will be affected by improvement work across Britain over the Christmas and New Year period can be found by visiting nationalrail.co.uk/Christmas.

 

Notes to editors

Christmas

Greater Anglia passengers

Norwich to London mainline

Sunday 23, Monday 24, Thursday 27, Friday 28, Saturday 29, Sunday 30 and Monday 31 December and Tuesday 1 January

A rail replacement bus service will run between Ingatestone and Newbury Park, where passengers can use their Greater Anglia tickets on the Central Line.

Trains will terminate at Ingatestone on Sunday 23, Monday 24 and Thursday 27 December and at Shenfield on Friday 28, Saturday 29, Sunday 30, Monday 31 December and Tuesday 1 January, but the rail replacement bus service to and from Newbury Park will run from Ingatestone from Sunday 23 December to Tuesday 1 January, except for Christmas Day and Boxing Day when there is no service.

Southend Victoria line

Sunday 23, Monday 24, Thursday 27 and Friday 28 December

A rail replacement bus service will run between Billericay and Newbury Park.

Saturday 29, Sunday 30, Monday 31 December and Tuesday 1 January

A rail replacement bus service will run between Southend Victoria and Newbury Park.

Stansted Express

From Sunday 23 to Tuesday 1 January, the Stansted Express service will be reduced to half-hourly, except for on Christmas Day, when there is no service, and on Boxing Day, when it will run between Tottenham Hale and Stansted Airport.

Felixstowe line

Saturday 22 December (from 18.50), Sunday 23, Monday 24 and Thursday 27

Buses replace trains between Ipswich and Felixstowe.

 

TfL Rail passengers

All dates below are inclusive

 Dates

Rail replacement

Sunday 23 – Monday 24 December

Shenfield and London Liverpool Street

Tuesday 25 - Wednesday 26 December

No service

Thursday 27 December

Shenfield to Liverpool Street until 10:30am and then Romford to Liverpool Street

Friday 28 December – Tuesday 1 January

Romford to Liverpool Street

   

 

Further work in 2019 - Greater Anglia services

Rail replacement services will run on the following weekends in 2019:

Dates

Rail replacement service

Saturday 12 January

 

Sunday 13 January

Ingatestone to Newbury Park

Saturday 19 January

 

Sunday 20 January

 

Saturday 26 January

 

Sunday 27 January

Ingatestone to Newbury Park

Saturday 2 February

Ingatestone to Newbury Park

Sunday 3 February

Witham to Newbury Park

Saturday 9 February

Ingatestone to Newbury Park

Sunday 10 February

Witham to Newbury Park

Saturday 16 February

Colchester to Ipswich

Sunday 17 February

Colchester to Ipswich

Saturday 23 February

Witham to Newbury Park

Sunday 24 February

Witham to Newbury Park

Saturday 2 March

Ingatestone to Newbury Park

Sunday 3 March

Ingatestone to Newbury Park

Saturday 9 March

Ingatestone to Newbury Park

Sunday 10 March

Ingatestone to Newbury Park

Saturday 16 March

Ingatestone to Newbury Park

Sunday 17 March

Ingatestone to Newbury Park

Saturday 23 March

Ingatestone to Newbury Park

Sunday 24 March

Ingatestone to Newbury Park

Saturday 30 March

Ingatestone to Newbury Park

Sunday 31 March

Ingatestone to Newbury Park

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Katie Mack
Media relations manager (Anglia route)
0330 8577 132
Katie.Mack@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk