Monday 2 Dec 2013

Rail improvement work at Ansford completes

Region & Route:
| Wales & Western: Western
| Wales & Western

The A371 road has fully reopened to road traffic today (2 December) as Network Rail completes the £1.2m improvement scheme to significantly strengthen the Ansford overbridge at Castle Cary.

The bridge now boasts a new 235 square metre concrete deck with all its steel elements repainted to protect the structure from corrosion.

Railway staff have clocked more than 9,000 hours since work began in July 2013 and they have been working round the clock where possible to minimise disruption. An encapsulation structure was also installed to protect the environment and allow works to continue despite poor weather conditions last month.

With final road surfacing now complete, Network Rail has now reopened both lanes of the A371 with only minor items to finish before all the work is complete.

Paddy Gregg, route delivery director for Network Rail Western, said: “We’d like to thank the community for their patience to enable us to complete this essential work on time and to plan. With the bridge work now completed, the community will now be able to gain from a much stronger structure that can carry up to 40 tonnes of road traffic. This also means a safer and more reliable infrastructure to support highway and rail services for many years to come.”

Road users have been able to access one lane of the A371 since 18 November.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office -Western route
MediaRelationsWestern@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk