While most of us were opening presents, enjoying turkey with all the trimmings and watching the Queen’s speech, a team of Network Rail engineers worked around the clock over the Christmas weekend to replace the main railway bridge in Diss in just 72 hours.
Andrew Munden, Network Rail’s route director for Anglia, explains: “The old bridge over Victoria Road was approaching the end of its life-span and needed to be replaced. Many more trains use this stretch of line than did when the bridge was first built so we’ve installed a new bridge designed to cope with the demands of a busy twenty-first century railway.”
Network Rail’s project team began working on site in November, carrying out preparatory work so that everything was ready to take advantage of the small amount of time available to replace the bridge over the Christmas weekend.
Once the last train had passed through on Christmas Eve, engineers moved in to dismantle the overhead power lines and cut and remove the existing tracks and ballast before the old deck was lifted out using a giant crane. The new pre-fabricated bridge deck was then inched into place before the ballast was replaced and the tracks and overhead power lines re-connected.
Mr Munden continued: “Our team worked around the clock, starting from the moment the last train passed through Diss on Christmas Eve. Their hard work and professionalism means we’ve been able to provide Diss with a new railway bridge in a single weekend – an impressive feat of engineering and teamwork.”
“I’d like to thank the people of Diss for their co-operation and apologise for any inconvenience caused during this essential bridge replacement. The previous bridge had served the town well for more than 100 years. I’m sure that the new bridge will do the same.”
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - South East route
020 3357 7969
southeastroutecomms@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk