NEW LANDMARK BRIDGE LAUNCHED INTO PLACE: Borough Viaduct 1

Tuesday 3 May 2011

NEW LANDMARK BRIDGE LAUNCHED INTO PLACE

Region & Route:
| Southern

A striking new railway bridge was successfully launched into place over Borough High Street during the bank holiday weekend, to play a vital role in increasing capacity, reducing delays and providing better connections for the 50m passengers who travel through London Bridge every year.

The uniquely-designed bridge, which is 72m long, six metres high and weighs 1,200 tonnes, was launched into place over the weekendv. Work started at 2am on Saturday morning and the road was re-opened to traffic by 5am Tuesday. The complicated engineering operation saw the bridge travel an average of 7mm per second using specialist machinery before being lowered into place, creating a new landmark.

Martin Jurkowski, Network Rail’s project director leading the London Bridge redevelopment, said: “The new Borough Viaduct will double the number of tracks coming out of the western end of London Bridge station, unlocking a major bottleneck and allowing us to provide two dedicated tracks for Thameslink services. It is a hugely important milestone in our plans to deliver modern stations, more trains and better journeys to and through the heart of London.”

“A project of this scale taking place in such a heavily built-up area required outstanding planning and innovation. Our solution was to build the new bridge on top of the new viaduct, which offered best value for money and minimal disruption for passengers, road users and the community.“

The bridge is part of the 507m-long Borough Viaduct which runs above the highly-built up Borough Market area. Finding space for new rail infrastructure in such a densely built up urban area has been a challenge, in some places it’s not more than 16cm away from existing buildings. The viaduct is nestled in-between listed buildings, its foundations are strategically located to avoid London Underground tunnels and the popular Borough Market that has been partly relocated during the works.

Mr Jurkowski added: “With the new bridge becoming a significant new local landmark we wanted to involve the community in its construction. We hosted hundreds of people over the weekend onboard a Routemaster bus which was positioned to provide a great view of the completion of this important milestone for the Thameslink Programme.”

With the bridge now in place, the final part of the installation will be completed as planned over the weekend of Saturday 7 - Sunday 8 May, during which time Borough High Street will be closed again. The same diversion routes will apply.

Notes to editors

ABOUT THE CONSTRUCTION OF BOROUGH VIADUCT

Before work on the viaduct began, Network Rail created a new trading space for Borough Market traders to replace the area needed for the work site. It is within the existing market site, off Winchester Walk, near the Cathedral. Known as the Jubilee Market, this area has been open for nearly two years, with a light, weatherproof canopy, and new facilities.

Work continues with the trustees and traders at Borough Market to enable the operation of the market to be maintained throughout construction. On completion, the Market will take up its old footprint, under the viaducts and its newly refurbished Victorian roof. It will also expand into a new purpose-built market hall giving the Market a high street entrance for the first time in centuries

Network Rail will also be building a new mixed-use development at 11-15 Borough High Street to replace a building that had to be demolished to space for the new bridge.

The Borough viaduct will rejoin the existing railway just outside London Bridge station. To build the southern stretch of the viaduct, some of the arches on Station approach will need to be remodelled.

By 2018 the new viaduct will link into a redeveloped London Bridge station, creating a bigger and better station for passengers.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - South East route
020 3357 7969
southeastroutecomms@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail