Network Rail submits final proposals for East West Rail phase 2: EWR phase 2 map

Friday 27 Jul 2018

Network Rail submits final proposals for East West Rail phase 2

Region & Route:
| National
| Eastern
| North West & Central

For the first time in over 50 years passengers could soon travel directly between Oxford and Bedford, and Milton Keynes and Aylesbury, unlocking the region’s housing potential and transforming the lives of residents for generations to come as the East West Rail project moves a step closer today (27 July).

A ‘mothballed’ section of the railway between Bletchley and Claydon Junction could be brought back to life, with plans for major signalling and track upgrades set to connect communities and businesses along the route and beyond, creating new opportunities for jobs, housing and economic growth for the future.

Work could begin as early as next year if Network Rail plans submitted to the Secretary of State for Transport to construct phase 2 of the project between Bicester and Bedford are approved.

The East West Rail project is being built progressively in phases, and once complete will create a world class rail link connecting Oxford, Bicester, Milton Keynes, Bedford and Cambridge, connecting communities and businesses to create more jobs, more economic growth, and more sustainable housing.

With phase 1 between Oxford and Bicester already complete, phase 2 proposes major track and signalling upgrades between Bicester, Bedford, Aylesbury and Milton Keynes, including the reinstatement of a ‘mothballed’ section of railway between Bletchley and Claydon Junction.

The proposed works will see major improvements to local travel, with the phased introduction of new rail journeys between:
• Oxford and Milton Keynes, with trains stopping at Oxford Parkway, Bicester, Winslow and Bletchley
• Oxford and Bedford, with trains stopping at Oxford Parkway, Bicester, Winslow, Bletchley, Woburn Sands and Ridgmont
• Milton Keynes and Aylesbury, with trains stopping at Bletchley, Winslow and Aylesbury Vale Parkway
Construction of phase 2 is subject to permission through a Transport and Works Act Order (TWAO), which if granted by government could allow major works to begin as soon as 2019.

Colin Murphy, head of consenting and environment for Network Rail, East West Rail project said: “The submission of the Transport and Works Act Order is a culmination of four years of work developing the scheme and follows three positive rounds of community consultation, where we’ve continually refined our proposal based on the views of the community and planning experts. We have carried out a comprehensive programme of consultation to understand the impact of our proposals and I’d like to thank everyone who contributed. As intended the feedback we received has informed our final proposals which we are submitting today. Once completed, the new railway will connect communities and businesses along the route and beyond, creating new opportunities for jobs, housing and economic growth”.

The TWAO application also coincides with East West Railway Company taking on new responsibilities for overseeing the successful delivery of the entire project.

Rob Brighouse, chairman at East West Railway Company said: “As a dedicated delivery body, East West Railway Company’s role is to streamline decision making and ensure the project is delivered quickly and cost-effectively.

“Today’s announcement by Network Rail is very welcome and shows our shared commitment to move all elements of the project from planning to delivery as quickly as possible.”

Councillor Mark Shaw, chairman of the East West Rail Consortium, which has campaigned for the reopening of this rail service since 1995, said: “East West Rail will drastically reduce journey times within the region, bringing key economic and cultural centres within easy reach of each other.

“After more than 20 years of campaigning, the submission of the TWAO is a hugely significant milestone, marking the final stage in acquiring permission to reopen the rail lines between Oxford and Bedford, and Aylesbury and Milton Keynes.”

Mayor Dave Hodgson, chair of England’s Economic Heartland’s Strategic Transport Forum, said: “The Government has made realising the huge economic potential of this region a national priority and East West Rail is fundamental to delivering this. It will support new jobs and housing and also be a catalyst for regenerating the towns and cities across its route.

“We now need the route between Bedford and Cambridge to be confirmed as soon as possible, so that delivery of the full scheme can be achieved within the Government’s stated target of the mid-2020s.”

Notes for editors:

East West Rail phase 2 is part of the wider East West Rail scheme to connect Cambridge to Oxford. The Western Section (phase 1), which operates services between Oxford and Bicester was completed in December 2016. The Western Section (phase 2) proposes to extend services from Oxford to Bedford and Milton Keynes to Aylesbury. The Central Section (phase 3) will see the full reconnection from Cambridge to Oxford, and the proposal is currently in development.

All submission documents are available at www.networkrail.co.uk/east-west-rail and paper copies can be viewed at the following locations:
• House of Lords library
• House of Commons library
• Bicester library
• Aylesbury Study Centre
• Winslow library
• Milton Keynes library
• Bedford library

The TWAO process:
1. Network Rail submits TWAO and publishes and serves notices;
2. A statutory period to receive representations until 7th September 2018;
3. the Secretary of State for Transport (SoS) may then decide on one of three options (1. Hold a public inquiry, 2. Hold a hearing, 3. Exchange written representations between relevant parties)
4. These would be led by an independent inspector who will make recommendations to the SoS
5. SoS makes a decision whether phase 2 can begin.

Public submissions are open until September 7th, 2018, and these should be made to the Department for Transport at transportandworksact@dft.gsi.gov.uk 

The East West Railway Company is a non-departmental public arm’s length body set up by the government to accelerate the East West Rail project.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk