Major milestone as signalling and track completed on Northumberland Line: Engineers working to install new track on the Northumberland Line, Network Rail (1)

Friday 9 Aug 2024

Major milestone as signalling and track completed on Northumberland Line

Region & Route:
Eastern
| Eastern: North & East

Engineers working to bring passenger services back to the Northumberland Line for the first time in more than 60 years have reached a key project milestone.

Network Rail and Siemens have installed and commissioned a new signalling system and major track work has been completed across the entire route, allowing trains to start running on the line for driver training.

Over the weekend (3 & 4 August 2024), the final section of signalling was commissioned between Bedlington and Benton Junction, where trains will leave the East Coast Main Line and serve passengers at six stations across the Northumberland Line.

This latest work follows an earlier system switch-on at Easter, where new signalling went live between Ashington and Bedlington, allowing freight services to operate between Bedlington and Lynemouth Power Station.

As well as the new signalling, Network Rail engineers have laid more than 25km of track and installed 22 sets of switches and crossings, the specialist equipment used by trains to change from one track to another. This will deliver smooth and reliable journeys for passengers when services start in the future.

This work has been a major part of the near £300m project to reconnect people living in Ashington, Bedlington, Blyth Bebside, Newsham, and Seaton Delaval to the rail network for the first time in more than 60 years.

Network Rail continues to support its partners in delivering this project, with the line expected to open for passengers from December 2024, with services starting at Ashington, Newsham and Seaton Delaval. The remaining stations will open next year.  

David Ball, Network Rail’s senior sponsor for the project, said: “This programme has been much more than dusting off some old infrastructure.

“Bringing this line back to life has meant renewing almost everything that remained since the last passenger service in the mid-60s, with a brand new signalling system and new track both key to getting the journey times and capacity – alongside the existing freight services - that will make this line a critical part of the North East rail network.

“A programme of this scale has brought challenges, but we are now tantalisingly close to being able to catch the train on this line again, and, together, we’re working flat out to complete the final phases of work to get the trains up and running.”

To find out more about the Northumberland Line, visit: https://www.northumberlandline.uk/

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Joshua Chapman
Media Relations Manager
Network Rail
joshua.chapman@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk