Network Rail installs new footbridge at Suggitt’s Lane ready to connect people in Cleethorpes with beachfront later this year

Region & Route:
Eastern
| Eastern: North & East

Network Rail has completed a major stage of work on a project to install a new accessible footbridge over the railway at Suggitt’s Lane in Cleethorpes.

Over the weekend (Saturday 25 and Sunday 26 September) engineers put part of the new bridge in place and installed ramps on the promenade side.

The new footbridge was built offsite to minimise disruption for people in the community. Once complete, it will have stepped and ramped access on both sides, connecting people in the seaside town with the beachfront.

Over the next few months, the rest of the structure will be put into place and lighting will be installed. Landscaping work on the approach to the bridge will also be carried out to develop walkways.

Work began onsite in June after the plans were approved by North East Lincolnshire Council and the project is expected to be completed in December.

Matt Rice, Route Director for Network Rail’s North and East Route, said: “We’ve made great progress over the weekend to get a section of the new footbridge into place. I know the local community will be keen to see access over the railway at Suggitt’s Lane restored as soon as possible, and so we’re moving at pace with the project.

“We want to thank everybody in the community, as well as any passengers who were impacted, for their patience whilst this important stage of constructing the new bridge took place. We’re continuing to work closely with North East Lincolnshire Council to complete this project by December.”

Cllr Stewart Swinburn, Cabinet member for highways and transport at North East Lincolnshire Council, said: “Things are obviously moving on quickly now with the bridge build, and like many others, I’ll be pleased to see it in place to reconnect our community in that area with the seafront – something that’s been missing for a while now.”

ENDS

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Kathryn Muffett
Media Relations Manager
Network Rail
01904 383180
kathryn.muffett@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk