Network Rail confirms next steps for Botley Road programme with critical focus on Thames Water’s sewer and mains connections

Region & Route:
Wales & Western: Western
| Wales & Western

Network Rail has today provided an update on the next steps in its Botley Road programme.

Thames Water is currently excavating a number of additional ‘trial holes’ on behalf of Kier, Network Rail’s principal contractor. Trial holes are a way to collect information on the ground conditions and services below the road and Thames Water will continue this work for the next five weeks (Monday - Friday only).  

These additional trial holes are needed to allow Thames Water to confirm whether it is possible to move its water main connection point further west along Botley Road towards Osney bridge. The two previous locations identified by Kier have been rejected by Thames Water due to operational concerns that any temporary works could impact on Oxford’s main water supply and sewer.

Since July 2024 Network Rail has been working with both parties to try and secure agreement to identify alternative locations for the diversions of these key utilities that serve Oxford and Oxfordshire, in consultation with the bus companies and local authorities. The current work being carried out by Thames Water will determine whether a new alternative location is possible.

Following completion of the physical trial hole works, Thames Water and Kier will then require a further four weeks to validate the designs, cost, and programme to carry out the diversions.

Once this information is shared with Network Rail, discussions can continue with funders around potential options for the overall scheme.

Francis McGarry, investment director Wales & Western at Network Rail, said: We apologise for the continued disruption and are grateful for the support and patience of the community whilst we undertake these works. We want to give clarity to residents, businesses and stakeholders as soon as possible. The work currently being carried out by Thames Water is vital to helping to find a way forward for this project. We will keep residents and the local community updated on any further developments as this work takes place. “

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Emily Maiden
Network Rail
Emily.Maiden@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk