Monday 11 Jun 2018
Investment in West Calder gives station accessibility a lift
- Region & Route:
- Scotland’s Railway: Scotland
West Calder station’s new, fully-accessible footbridge and lifts have opened to passengers, as part of a multi-million-pound transformation of the West Lothian station.
The installation of the £2.7 million bridge provides step-free access via lifts to both platforms and has been completed as part of the Scottish government-funded Shotts Line Electrification project, will improve access within stations for people with impaired mobility, travelling with luggage, children, cycles etc.
Constructed over the last ten months, the bridge includes lifts and stairs and replaces the old station footbridge which was no longer fit for purpose. The new bridge and stairs opened in April to enable the old bridge to be craned out and the lifts commissioned for service.
Construction work on the new structure was delivered over a 10 month period from a purpose-built site compound established initially to enable work on the A71 road bridge - completed early in 2017. The new bridge is part of wider work on the Shotts line being delivered by Network Rail ahead of the electrification of the route in 2019.
The old bridge, which will find a new home on Bo’ness heritage railway was removed by a 130t crane in 3 lifts – with work taking place during the 10 day closure of the line back in April so as to minimise disruption for passengers.
During work pedestrian access was maintained between platforms as the old footbridge remained open throughout while the station was open. The footbridge was only closed at night to enable work on the new bridge – constructed immediately to the east of the old structure.
The addition of the new and removal of the old bridge structures meant there was a need to resurface the approach footpaths, sections of the platforms and to make it easier for passengers to access the new bridge.
Kevin McClelland, route delivery director for infrastructure projects, said: “We are continuously seeking opportunities to make stations more accessible and the new footbridge at West Calder will help ensure that everyone in the community has the opportunity to easily access train services and thus enables more people to travel by train.
“Opening the new bridge is another important milestone for the electrification project – with the added bonus of enabling the old bridge to be relocated and preserved at Bo’ness heritage railway – which is great to see.
“We have cleared structures all along the route to avoid them being an obstruction to the safe running of the overhead wires which will enable electrification. Doing this in the station also brings the benefit if significantly improving accessibility which will transform the travelling experience for everyone using the station which is fantastic”.
The work on the new footbridge at West Calder station was delivered by contractor Bam Nuttall on behalf of Network Rail.
Electrification of the line across North Lanarkshire and West Lothian coupled with improvements at stations will transform the journey experience for passengers who will enjoy the benefits of improved services for many years to come.
Notes to Editors
Network Rail is on target to deliver the next phase of electrification of central Scotland’s railway network, between Holytown and Midcalder junctions – which will complete the electrification of the Shotts line’ between Edinburgh & Glasgow by March 2019.
The works comprise electrification of 74 single track kilometres of railway between Holytown Junction and Midcalder Junction to create when completed, the fourth fully electrified line between Edinburgh and Glasgow.
Additionally, the advanced clearance programme sees 17 structures on the line removed or replaced with an increase in the heights of parapets (side walls) at a further 10 bridges. Work also sees new station footbridges at Addiewell and West Calder.
The project is a Scottish Government investment and part of Network Rail’s UK-wide railway upgrade plan.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk