Network Rail’s £45m project to upgrade the line between Swindon and Kemble was successfully completed over the bank holiday weekend, paving the way for greater capacity, reduced journey times and a better experience for passengers.

The infrastructure upgrade along the route included the reinstatement of the second line between Swindon and Kemble, improvements to earthworks to accommodate the new track, and the installation of new signalling equipment which will safely control the movement of trains.

The new infrastructure provides increased capacity, which will be crucial to meet future passenger demand and will reduce delays for a more reliable service. These improvements will also be essential to enable trains from south Wales to be diverted along this route when Bristol Parkway station and the Severn Tunnel are closed for electrification work.

Simon Maple, Network Rail’s route programme and project sponsor, said: “Now that our work is complete, passengers can look forward to fewer delays and reduced journey times in the future. It also means we can minimise the disruption caused by our electrification work and ensure the region gets maximum benefit from a modern, electric railway.

“As is the case with most major works, a certain amount of disruption is unfortunately unavoidable and I would like to thank passengers and local residents for their continued patience and understanding.”

Other improvements incorporated as part of the upgrade project include the installation of additional signals between Kemble and Standish Junction, level crossing upgrades at Minety and Purton Collins Lane and the installation of a new footbridge in Stroud.

Rob Mullen, First Great Western’s general manager central, said: “These are vital infrastructure works to help pave the way for increased capacity and reduced journey times, and better performance and punctuality that electrification and new electric trains will bring for future services.

“We have worked closely with our colleagues at Network Rail to keep disruption to a minimum but I must thank our customers for their understanding and patience as we seek to make the improvements that we know they want to see.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office -Western route
MediaRelationsWestern@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk