Monday 5 Jan 2026
Christmas work delivers a better railway for passengers
- Region & Route:
- Eastern: Anglia
Rail teams across Anglia have successfully delivered a range of engineering work over the festive period which has improved the railway for passengers.
While millions of people tucked into their Christmas dinners, hundreds of engineers were out in force to deliver major renewals projects, undertake maintenance and repairs at a time when the railway is generally much quieter.
Liverpool Street station
The UK's busiest station, London Liverpool Street was closed for eight days to allow work to continue on the roof renewal project. During that time, 224 roof panels above the concourse were replaced along with 53 access (maintenance) hatches. Additionally, vital work to the roof's rainwater drainage system was done so that the station can cope with more frequent and intense rain storms. By the end of the eight days, a huge scaffolding frame was removed from platform 7/8 so passengers can see how the new roof panels are letting more light into the station.
Bethnal Green
While London Liverpool Street station was closed for Christmas, we refurbished old sleepers and seven sets of points (the moveable sections of rail which allow trains to move between tracks) on the West Anglia main lines at Bethnal Green to improve reliability for Greater Anglia and and London Overground Weaver line passengers.
London Overground Mildmay line
A major piece of work was completed on the London Overground Mildmay line as ten sets of points were replaced between Camden Road and Richmond/Shepherd’s Bush. Rail crews worked in shifts, 24 hours a day for 11 days to replace these major sections of track across complex rail junctions, and completed the work on time to handback the line to train services on Monday 5 January.
Cambridgeshire
Across Cambridge, Network Rail and signalling specialists from Alstom have been hard at work to complete the critically important second stage of the Cambridge re-signalling project (C3R). Just after midnight on Christmas day, the aging signalling panel in the Cambridge powered signal box (PSB) was switched off for the last time after over 40 years of service. A message of 'FAREWELL' was displayed on the panel while the old mechanical relay room fell silent.
Over 11 days, new digital workstations were installed and switched on while new computer equipment using Alstom's signalling control programme was switched on and tested to make sure the new control systems had successfully been integrated. The new digital workstations included the four track configuration for Cambridge South station for the first time. New signals were also physically installed on gantries while old, redundant signalling cabinets were removed.
At Meldreth Road, the level crossing has reopened to road users a week early after the team successfully upgraded the level crossing crossing equipment to a manually controlled barrier with CCTV. This crossing now uses full barriers that are connected to the main signalling system and are operated remotely using CCTV cameras, making the crossing safer for all road users.
At Cambridge South station, work continued inside to fitout the electrical and mechanical systems of the new station which is expected to open later in 2026.
Other engineering work over the festive period
Track teams were out on site at Ipswich changing old timbers just outside the station and tamping (a process of packing the ballast under the track) over a 2.1km stretch, helping to give passengers a smoother, safer journey on the busy main line. Further track work to replace the rails also took place near Great Bentley.
A new buffer stop was also installed at Clacton-on-Sea station for platform 4, providing a greater level of protection at the station.
And at Kennedy Road in Barking, a replacement pedestrian footbridge was opened, reconnecting the communities either side of the railway for the first time since 2022.
Katie Frost, Network Rail's route director for Anglia said: "We've delivered major renewals and repairs over the festive period and I want to take this opportunity to thank all our passengers, for their patience while we have completed these important engineering work across our network.
"There is never a good time to close the railway, but over Christmas the railway sees passenger numbers drop by 50% and this is the best opportunity to complete as much work as we can when the railway is quieter than usual."
Weekend engineering work across some routes will continue into 2026 and we encourage passengers to check their journey plans before travelling by visiting nationalrail.co.uk or the train operator websites.
Notes to Editors
Engineering work across the Anglia route continues into the New Year. Our press releases on these planned engineering works in early 2026 can be found here:
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail Anglia Press Desk - Stephen Deaville
Senior Communications Manager
Network Rail
0330 8577 132
07734647627
AngliaPressDesk@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk