CHRISTMAS DOESN’T STOP WEST COAST MAIN LINE PROGRESS: Rugby Birdcage Bridge Removal

Tuesday 2 Jan 2007

CHRISTMAS DOESN’T STOP WEST COAST MAIN LINE PROGRESS

Region & Route:

While the country sat down for its Christmas dinner and enjoyed the New Year festivities, Network Rail engineers worked through the holiday period to continue progress on major improvements to the West Coast Main Line through the Midlands.

The Christmas period was used to undertake several major bridge replacements on the Trent Valley Four Tracking project which will increase the capacity on the West Coast Main Line from 2 to four tracks between Tamworth and Armitage with Handsacre in Staffordshire. In Warwickshire, work continued to deliver a £190 million project to improve the station facilities and relieve a major bottleneck at Rugby. Engineers also removed a redundant bridge over the line south of Rugby station. With no break for New Year celebrations engineers worked solidly 24 hours a day to replace 3 bridges, remove a level crossing and relay track in 5 different locations in the Trent Valley. Over the 10 day holiday period work was completed on: · Two bridge replacements in Armitage with Handsacre. New Road bridge and the Trent and Mersey Canal bridge were replaced and new track and signalling equipment installed. · Work to realign track over Huddlesford Lane and the Coventry Canal bridge, in Huddlesford. · A bridge replacement in Whittington. Burton Road rail over road bridge was replaced and new track and signalling equipment installed. · The last level crossing between London Euston and Crewe was removed at Hademore near Tamworth and replaced with a road bridge. · At Rugby, engineers used a 1200 tonne crane to lift out the old “Birdcage” bridge south of the station on Christmas Day. The bridge, built in 1898 and disused since the 1960’s was in a poor condition and need to be removed before it presented a risk to passengers using the West Coast Main Line underneath Peter Henderson, Network Rail’s Projects & Engineering Director said: “The huge scale of work on the West Coast project over the Christmas break was quite phenomenal. The fact that it has been completed on time and on budget is a testimony to all the staff that gave up their holiday to ensure this important part of project was completed. Network Rail is committed to growing the railway and increasing capacity for future passengers and the work we are doing at Trent Valley and Rugby is vital to the growth of the West Coast Main Line.” Both projects are set to be completed by December 2008 and will increase the capacity of the West Coast Main Line through the Midlands, enabling train operators to deliver more services from the end of 2008.

Notes to editors

Time lapse video footage of Network Rail engineers installing two new bridges at Armitage over Christmas 2006 is available. Additional photography is also available, for more information call Ben Herbert on 0121 345 3100 More than 55,000 passengers use the West Coast Main Line every day. Closing the railway for 10 days over Christmas enabled these large scale projects to be completed while causing minimal disruption at a time of year when fewer passengers use the railway The Trent Valley and Rugby projects represent the final part of the £8bn upgrade of the West Coast Main Line. The Trent Valley project involves the doubling of the railway to four tracks along a 19km section between Armitage and Tamworth to remove a major bottleneck while at Rugby work to remodel the track and improve the station will also relieve a bottleneck while improving facilities for passengers using Rugby station. As well as widening the tracks there are 37 structures to be replaced or modified as part of the Trent Valley project. The majority of the engineering work on these structures has now been completed and the project itself is now 40% complete. Hademore Level Crossing was one of the most misused crossings in the West Midlands. It was also the last Level Crossing on the West Coast Main Line between Crewe and London Euston. The West Coast Project is scheduled to be completed by the end of 2008.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk