Monday 5 Aug 2024
Bridge replacement in Hackney: 16 days of intensive works completed on time
- Region & Route:
- Eastern: Anglia
Network Rail is thanking passengers and the local community after it finished a key stage of a major project to replace a deteriorating bridge.
London Overground trains started running between Liverpool Street – Chingford again on Monday 5 August as planned after the bridge works closed the line for 16 consecutive days. There were also changes to Stansted Express and some Greater Anglia services.
The project is to replace a 150-year-old bridge in Hackney that carries the junction of Downs Park Road and Bodney Road over the railway. The bridge was in very poor condition, with a full replacement needed to avoid an unplanned closure and keep passengers and road users moving in future.
Engineers began the 16 days by demolishing the old bridge, before starting to build the new one. Milestones during the project included:
- Installing special access to the site, lowering the overhead lines and protecting the track
- Demolishing the brick arches and parapet of the old bridge, and lifting away the metal girders
- Building the structure of the replacement bridge by lifting in concrete cill beams, infill beams and the new steel parapet
- Taking down the scaffolding and putting the overhead lines back up ready for trains to run
Although the railway under the bridge has now reopened, there is still lots of work to do, including:
- Relocating utility services
- Concreting the bridge deck
- Rebuilding the road and pavement, and putting back the street furniture
All work is expected to be completed, and Downs Park Road fully reopened, by early 2025.
The project is being carried out by Network Rail’s contractor, Murphy.
Click below to watch a video filmed shortly before the end of the 16 days showing the progress on the project:
Train services will also be affected by follow-up works on the bridge on the following dates, so passengers should check before they travel:
- Saturday 17 and Sunday 18 August
- Sunday 1 September
- Sunday 8 September
In addition to the bridge replacement over the 16 days, Network Rail engineers carried out maintenance at sites up and down the Chingford line. This included refurbishing critical sets of points, improving the condition of the track ballast, and testing and replacing signalling power supply cables. London Overground also undertook additional work at a number of stations, including repairs and refurbishment of the stairs at Clapton and repairs to station canopies to protect heritage features at Chingford, Clapton and Walthamstow Central.
Simon Milburn, Network Rail Anglia infrastructure director, said: “Thousands of people travel under and over this bridge every day by rail and road, and our project is vital to keeping their future journeys safe and reliable. We’re sorry to have caused the disruption to people’s journeys this summer but the replacement bridge will serve the community for generations to come.”
Rory O’Neill, TfL’s general manager for London Overground, said: “I would like to thank customers for their patience while Network Rail completed these essential bridge replacement works. We understand closures such as these can cause inconvenience for some customers but they are vital to ensure we can continue to offer a safe and reliable service for many years to come.”
Jamie Burles, Greater Anglia managing director, said: "We would like to thank customers for their patience and understanding while this work was carried out. The bridge is very well used, and the essential works were very important to make it safe and fit for the future. Some follow-up works will also take place in August and September and customers are advised to check before they travel.”
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Richard Cooper
Communications manager
Network Rail
0330 8577 132
richard.cooper3@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk