Roads reopen after £30 million bridge deck upgrade in Camden
- Region & Route:
- Eastern
- | Eastern: East Midlands
All roads have reopened on a new bridge deck installed over the railway in north London – marking one of the £30 million project’s final milestones.
The 160-year-old structure at Agar Grove, Camden, was completely replaced in just nine days in late 2024, to improve journeys on the Midland Main Line.
Rail journeys were able to resume on December 30 following a successful handover, after which the crane was dismantled and utility supplies reinstated.
One lane of traffic was opened in February and the temporary footbridge was removed the following month.
The bridge deck’s road surface was completed last weekend, allowing the area to reopen to road vehicles from today (Monday 12 May).
Mark Budden, Network Rail route director, said: “The Agar Grove project was years in the making, meticulously planned at every stage and successfully carried out.
“As we approach the home straight, it is important to reiterate how extremely grateful we are to the residents living nearby for their understanding as we carried out this crucial work.”
The bridge deck replacement was started after the last train on the night of 20 December last year.
Within days, the old structure had been demolished, and by 29 December the new beams, parapets and bridge deck had been erected.
During this same tight timeframe, the railway track and overhead line equipment, which powers trains, was reinstated, allowing services to resume as planned on 30 December.
Network Rail teams made the most of the time when trains were not running to carry out 50 smaller tasks like vegetation management, track maintenance and renewing power cables.
A footpath route across the bridge from St Augustine’s Road, Camden is set to open later this week, with work to complete all remaining footpaths being finished in mid-June.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Gareth Dennison
Media relations manager, Eastern region
Network Rail
07561 874858
gareth.dennison@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk