Work underway to repair flood-damaged West Highland Line

Region & Route:
Scotland’s Railway: Scotland

Engineers will be working around-the-clock to repair the West Highland Line after severe flooding on Monday night caused significant damage between Roy Bridge and Tulloch.

The line will remain closed between Fort William and Crianlarich until early next week while engineers work to carry-out repairs at three sites.

The repairs will include rebuilding a section of the line where over 400 tons of material has been washed away from beneath the track. Engineers will need to rebuild the embankment beneath the line and relay the track before the railway can reopen.

Due to the complexity of the repairs and the need to wait for the flooding to subside before beginning work, exact timescales for the reopening of the line cannot be confirmed at this time.

Liam Sumpter, Network Rail Scotland route director, said: “Flash-flooding has caused significant damage to the railway and we are working hard to repair and reopen the line as quickly as we can for our customers.

“The damage to the line is extensive and it will take several days for our engineers to complete repairs.

“We understand the difficulties this incident will cause for our customers and local residents and will reopen the line as soon as we can.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk