Work to upgrade the Southend Victoria line resumes this weekend: Southend OLE works  2 - May 2019

Thursday 29 Aug 2019

Work to upgrade the Southend Victoria line resumes this weekend

Region & Route:
Eastern: Anglia

Work to improve journeys for passengers by upgrading the overhead wires between Shenfield and Southend Victoria resumes this weekend until the end of March 2020.

Network Rail is replacing 128km of overhead wires between Southend Victoria and Shenfield with a new auto tension system that adapts to temperature changes. This will improve the reliability of services for years to come for passengers on the Southend Victoria line.

The winter weekends phase of works is due to complete by the end of March 2020, two months earlier than originally planned, with six fewer weekend closures and 11 mid-week closures owing to an acceleration of the delivery programme.

Following this, there will be a final closure for works over the weekend of 18-19 April 2020 that will enable us to replace the track ballast to enable efficient drainage for the new infrastructure.  

When complete, 320km of wires and 200 structures that support the wires at the correct height and tension will have been replaced on the entire route that runs between London Liverpool Street and Southend Victoria as part of the £46m project.

Mark Budden, Network Rail’s route director for Anglia, said: “We’re entering the final phases of this much-needed upgrade, which will bring greater reliability for passengers on this busy line.

“I know that there is a lot of weekend disruption for passengers over the autumn and winter, and I’m sorry their journeys will be more difficult during this time while we carry out the upgrades to the overhead lines.

 “Once the upgrade is complete it will lead to a much more reliable service for everyone using the Southend line, reducing delays and cancellations caused by very hot temperatures.”

Jamie Burles, Greater Anglia managing director, said: “We’re into the final stretch of this major project to improve the reliability of this stretch of our network, which combined with our new trains, will modernise journeys for our Southend customers.

“I’d like to thank customers for their patience throughout these engineering works, and assure them that while Network Rail finishes the project we will ensure that passengers can always complete their journeys, even if part of it is by bus.”

In order to carry out the work safely, work will be taking place over several  weekends between September and the end of November.

In December, works will be scaled back to Sunday mornings only from 2.15am – 9.00am on 1, 8, 15 and 22 December.

There are no services on Christmas Day and Boxing Day, and a rail replacement service will operate between 27 December and 1 January 2020, with work planned to focus on the complex junction at Wickford.

A final phase of weekend closures starts the weekend of 25-26 January 2020 and continues each weekend until 28-29 March 2020 (apart from 8/9 February when the line will be open).

There will be a final closure over 18-19 April 2020 to replace the track ballast for efficient drainage for the new infrastructure.  

While the works are being carried out, buses will replace trains and further details are available on the Greater Anglia website.

Saturday 31 August - Sunday 1 September Buses will replace trains between Shenfield and Southend Victoria / Southminster all weekend.
Saturday 7 September - Sunday 8 September Buses will replace trains between Shenfield and Southend Victoria / Southminster all weekend.
Saturday 14 September - Sunday 15 September Buses will replace trains between Shenfield and Southend Victoria / Southminster all weekend
Saturday 21 September - Sunday 22 September Buses will replace trains between Shenfield and Southend Victoria / Southminster all weekend

Saturday 28 September

Sunday 29 September

 

Trains running

Buses will replace trains between Shenfield and Southend Victoria / Southminster all weekend

Saturday 5 October - Sunday 6 October Buses will replace trains between Shenfield and Southend Victoria / Southminster all weekend.
Saturday 12 October - Sunday 13 October Buses will replace trains between Shenfield and Southend Victoria / Southminster all weekend
Saturday 19 October - Sunday 20 October Buses will replace trains between Shenfield and Southend Victoria / Southminster all weekend
Saturday 26 October - Sunday 27 October Buses will replace trains between Shenfield and Southend Victoria / Southminster all weekend
Saturday 2 November - Sunday 3 November Buses will replace trains between Shenfield and Southend Victoria / Southminster all day
Saturday 9  November - Sunday 10 November Normal train service all weekend
Saturday 16  November - Sunday 17 November Buses will replace trains between Shenfield and Southend Victoria / Southminster all day
Saturday 23  November - Sunday 24 November Buses will replace trains between Shenfield and Southend Victoria / Southminster all day

Saturday 30  November

Sunday 1 December

Train service as normal

Work happening between 2.00am - 9.00am only

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Martin Spencer
Martin.Spencer2@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk