Work to deliver car park improvements for passengers reaches the half way point: Car park renewals 5

Wednesday 8 Jul 2020

Work to deliver car park improvements for passengers reaches the half way point

Region & Route:
Southern: Wessex
| Southern

The work to improve station car parks across the South has reached half-way as part of Network Rail and South Western Railway’s commitment to improve facilities for passengers.

Fourteen stations have been earmarked for improvements including: Worcester Park and Witley stations in Surrey, Salisbury in Wiltshire, and Overton, Farnborough, New Milton and Hinton Admiral stations in Hants.

Since the start of April, there have been upgrades to seven stations across the South Western Railway network including Sunningdale, Effingham Junction and Weybridge in Surrey, Botley in Hampshire and Honiton in Devon.

Work is due to start on four car parks this weekend and early next week, with the work on the remaining three car parks expected to finish by the autumn.

The work at the car parks included resurfacing work, repainting lines, marking out safe walking routes, removing trip hazards and improvements to drainage so rain water doesn’t form puddles.

This is part of Network Rail’s commitment to make the experience better for passengers and follows on from resurfacing work at Fleet station in February.

Mark Killick, Network Rail Wessex route director said: “The improvements will make travelling to and from the stations much easier, and provide passengers with a better experience.

“While we carry out this work, we will try to keep passenger disruption to a minimum.”

Alan Penlington, customer experience director for South Western Railway said: “We welcome these improvements to car parks at our stations.

“The addition of the walkways will help to ensure customers using our services will be able to travel to and from the station safely.” 

The following car parks have been upgraded:

  • Effingham junction
  • Claygate
  • Sunningdale
  • Weybridge
  • Horsley Claygate
  • Botley
  • Honiton

The following car parks are going to be improved:

  • Salisbury (10-11 July)   
  • New Milton (12 July)
  • Hinton Admiral (13-14 July)  
  • Overton (15 July) 
  • Worcester Park (tbc)
  • Farnborough (tbc)
  • Witley (tbc)

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Martin Spencer
Martin.Spencer2@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk