Winchburgh works to finish on time for passengers: winchburgh tunnel slab tracking july 24

Friday 24 Jul 2015

Winchburgh works to finish on time for passengers

Region & Route:
Scotland’s Railway: Scotland

The ScotRail Alliance has today (Friday) confirmed that the Edinburgh-Glasgow main line will reopen as planned on Monday (July 27) following the successful, on-time completion of a six-week project to upgrade Winchburgh Tunnel.

Engineers – who have been working to lower and relay track through the 330m-long tunnel and install equipment to enable electrification of the line – will complete the 44-day, £17m project to schedule this weekend.

All ScotRail passenger services affected by the work, which has been the most significant piece of engineering on the line since the Victorian era, will resume normal service from Monday morning.

Derek Mackay, Minister for Transport and Islands, said: “I am pleased that this major programme of works at the Winchburgh Tunnel has been completed both on time and within budget.

“Completion of the work at Winchburgh is a key milestone in the Edinburgh Glasgow Improvement Programme, which is a comprehensive programme of improvements to Scotland’s rail network.

“Upon completion this will deliver a 20% reduction in journey time and allow the rail network to carry 30% more passengers between Scotland’s two biggest cities.

“I would like to thank all the passengers whose travel plans have been affected for their patience over the past six weeks.”

Phil Verster, ScotRail Alliance managing director, added: “The on-time completion of a project of this size and complexity in just six weeks is a significant achievement for all of the engineers involved.

“It also demonstrates how, by working more closely together, the rail industry in Scotland can deliver vital enhancements to our network while also keeping passengers informed and on the move.

“This is a massive piece of work that will help deliver long-lasting benefits to our customers. Electrifying the line between our two biggest cities will allow us to run faster, longer, greener trains that will cut journey times and increase the number of seats available on this key route.

"We would like to thank our customers for their patience and co-operation while the tunnel has been closed – passengers adapted very quickly to the unavoidable short-term disruption and we are very grateful for their understanding and support."

Working around-the-clock to limit disruption to passengers as much as possible, engineers have completed over 80,000 hours of work on the project since it began on June 13, pouring over 2,000 tonnes of concrete and laying nearly 200 slabs of track through the newly lowered tunnel.

Additional staff were also deployed to stations along the route to help advise passengers affected by the project – which impacted principally on services on the Glasgow-Falkirk High-Edinburgh and Dunblane/Stirling-Edinburgh lines.

Part of the Scottish Government-funded, £742m Edinburgh Glasgow Improvement Programme (EGIP), the refurbishment of Winchburgh Tunnel is a vital step towards the electrification of the main Edinburgh-Glasgow Queen Street line by 2016.

Once complete in 2016, electrification will mean faster, greener and longer electric services on the route with more seats and more space for customers.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk