West Highland line reopens for passengers: Lochailort July 11

Monday 13 Jul 2020

West Highland line reopens for passengers

Region & Route:
Scotland’s Railway: Scotland

The West Highland line reopened for passengers this morning following the successful completion of repair works between Fort William and Mallaig.

The line had been closed by damaged tracks at Lochailort after extreme rainfall caused a nearby stream to overflow and wash-away a section of the railway embankment beneath the line.

Engineers worked around-the-clock to replace more than 1,600 tons of material washed away by the flash-flood on June 25 and to install new under-track drainage systems and relay over 80metres of track.

Work was carried out to improve drainage on third-party land to reduce future risk to the railway and the project team also improved the flood defences of a nearby lineside neighbour affected by the extreme weather.

Liam Sumpter, Network Rail Scotland route director, said: “With the easing of lockdown and the reopening of the tourism sector, it was vital that we completed these repairs quickly to help support the local economy in the West Highlands.

“The line had been extensively damaged and our engineers have been working around-the-clock to reopen the railway for our customers.

“I’d also thank our contractors – QTS and Story – for their close collaboration during this project, which has been vital to getting passengers moving again.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk