Carstairs Junction will be modernised as part of a £164m Scottish Government investment in the railway.  

Passengers are being reminded that the West Coast main line will close for 16 days from Saturday (March 4) as engineers deliver a vital programme of work to upgrade Carstairs Junction.  

The closure of the line, between March 4 and March 19, is the first phase of a three-month programme of work which will also see trains diverted and journey-times extended all services between Glasgow/Edinburgh and Carlisle until June.

The work is part of a £164m Scottish Government investment to modernise the key junction for passenger and freight services.

Engineers will simplify and upgrade the track-layout to clear an existing bottleneck on the network, making it more reliable and able to better cope with passenger and freight demands.

Work on this strategically important route will be complex and Network Rail will complete it in three phases designed to manage the effect on services in the least disruptive way.

During the first phase of the project there will be no direct services to Glasgow Central and Edinburgh on the West Coast main line through Carstairs.

The closure of the junction will affect cross-border operators including Avanti West Coast, Caledonian Sleeper, CrossCountry Trains, London North Eastern Railway and TransPennine Express, who will be operating via diversionary routes or offering alternative journey options during this time.

Liam Sumpter, Route Director, Network Rail Scotland, said: “Carstairs Junction is coming to the end of its life cycle and with the volume of freight and passenger trains passing through each week it’s important that we modernise this part of the network.

“By completing this crucial upgrade work we will improve the capabilities and reliability of this strategically important junction, providing better future journeys for passengers and more capacity for freight.

“There’s never a good time to close such an important line but this is a huge and extremely complex piece of work that will safeguard the future of the route for years to come.

“We appreciate that this will cause some inconvenience and would like to thank customers for their patience during this time.”

Notes to Editors

Notes to editors

During the first phase of the project – between Saturday March 4 and Sunday March 19 - there will be no direct services to Glasgow Central and Edinburgh on the West Coast main line through Carstairs.

Phase two of the work, taking place between Monday March 20 and Friday April 21, will see part of the junction re-opening, allowing some trains to run directly to Edinburgh – and via diversion routes to Glasgow – on weekdays, however, journey times will be longer than normal.

The final phase, between Saturday April 22 and Sunday June 4, will see most services return to normal during weekdays with the junction fully closed each weekend.

During the later phases of the project, there will be no direct services between Glasgow Central or Edinburgh and Carlisle on the West Coast main line each weekend.

The closure of the junction will affect cross-border operators including, Avanti West Coast, Caledonian Sleeper, CrossCountry Trains, London North Eastern Railway and TransPennine Express, who will be operating via diversionary routes or offering alternative journey options during this time.

Services operating on the East Coast main line during this time are also likely to be busier than normal.

There will be no ScotRail services to or from Carstairs for the full three-month period. ScotRail will run a range of alternative journey options throughout with Carstairs station re-opening on Tuesday May 30.

Carstairs junction sits 26 miles to the south-east of Glasgow on the West Coast main line. Currently the junction requires regular maintenance work as much of the infrastructure through the area is reaching the end of its operational lifespan. Speed restrictions are often imposed which can affect performance.

The layout of the junction is no longer suited to today’s pattern and volumes of service with 200+ services passing through the junction on an average midweek day.

Enabling works for the project have been underway since 2020 and the work delivered during the line closure will see over 200 engineers working 24/7 to upgrade the junction.

The new power supply being installed will allow engineers to switch off the overhead lines remotely to carry out maintenance, reducing the amount of time the railway is closed in future. The improvements will also bring reduced overall journey times through the removal of a 50mph speed restriction.

Passengers are advised to check with National Enquiries www.nationalrailenquiries.co.uk or with their train operator for the alternative travel plans for their route.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Eddie Harbinson
Media Manager
Network Rail
edward.harbinson@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk