West Coast Main Line to close between London Euston and Watford due to emergency bridge work: Oxhey Grange footbridge

Friday 4 Sep 2026

West Coast Main Line to close between London Euston and Watford due to emergency bridge work

Region & Route:
North West & Central
| North West & Central: West Coast Mainline South

Passengers are being urged to avoid travel if they can during major railway disruption on Sunday 20 September until 4pm when Network Rail removes Oxhey Grange footbridge near Watford in an emergency operation to keep the railway safe.

The bridge, which crosses the West Coast Main Line south of Watford Junction, was closed on 26 July after routine inspections revealed it had deteriorated more quickly than expected and required urgent intervention. Engineers have decided it must now be removed as soon as possible to protect passengers, railway workers and the local community.

To complete the work safely, Network Rail will close all four West Coast Main Line tracks and the adjacent London Overground Lioness line beneath the bridge from midnight on Saturday 19 September until 4pm on Sunday 20 September. The bridge will be lifted out in a single operation using a specialist 100-metre-tall heavy-lift crane capable of lifting 1,200 tonnes. This approach significantly reduces the amount of time the railway needs to be closed compared with alternative removal methods.

The closure will affect journeys between London Euston and Watford Junction until 4pm, with amended services operating across the West Coast Main Line.

Passengers travelling between London, the West Midlands, North West England and Scotland are being advised to avoid travel if they can. Those who need to make journeys should check before travelling and allow extra time. Updated timetables for Sunday 20 September will be available in journey planners from Monday 7 September.

During the closure:

  • Avanti West Coast services to and from Scotland and North West England will start and terminate at Milton Keynes Central, with additional services starting and terminating at Rugby.
  • London Northwestern Railway services will operate between Milton Keynes Central and destinations to the north, with an hourly shuttle service running between Milton Keynes Central and Watford Junction.
  • London Overground Lioness line services will be limited to two trains per hour between Euston and Willesden Junction, while London Underground Bakerloo line services will continue to operate normally.
  • Passengers travelling between England and Scotland will still be able to travel using alternative rail and replacement bus arrangements, although journey times will be longer than usual.

 

Gary Walsh, director for Network Rail’s West Coast South route said:  "Following a routine safety inspection, Network Rail closed the footbridge at Oxhey Grange after identifying significant deterioration of the structure. The safety of residents, bridge users, railway colleagues and passengers remains our top priority, and further assessments have shown the bridge now needs to be removed as soon as possible.

"We know this work will disrupt journeys on Sunday 20 September and we're sorry for the inconvenience. By using a specialist heavy-lift crane, we're able to remove the bridge in a single operation and reopen the railway as quickly as possible. Passengers are advised to avoid travel until 4pm and allow extra time for their journeys.

"At the same time as progressing plans to safely remove the existing bridge, we are continuing to develop proposals for its replacement and will engage with the local community as this work progresses.”

Jonny Wiseman, customer experience director at London Northwestern Railway, said: “This work is crucial for maintaining the safety of the railway and I would like to thank customers for their patience while Network Rail carries out the operation.

“Rail replacement buses will be running and we are working closely with industry partners to offer alternative rail routes for those travelling to and from London. I encourage anyone planning to travel on the affected date to plan their route in advance and leave extra time for their journey.”

Rory O’Neill, TfL’s general manager for London Overground, said: "We know how important this emergency work is to the safe and reliable operation of the railway and would like to thank customers for their patience while Network Rail carries out this bridge replacement work. We encourage customers to check before they travel and allow a little extra time for their journeys when using the Lioness line."

Chris Liptrot, Operations Director at Avanti West Coast, said: “While Network Rail carry out this major piece of work, there’ll be changes to our services to and from London Euston on Sunday 20 September.

“We’re working with Network Rail and industry partners to ensure customers know what this will mean for their journeys to or from London once our timetable is confirmed on Monday 7 September. Customers planning to travel during this time are strongly advised to check the Avanti West Coast and National Rail Enquiries websites from next week for the latest information.”

Preparatory work is already under way at the site, including structural monitoring, site surveys and construction of a crane platform. Temporary speed restrictions are also in place beneath the bridge as a precaution while removal plans are completed.

Network Rail is continuing to develop plans for a replacement crossing and will engage with local residents and stakeholders as the project progresses.

Notes to Editors

Avanti West Coast:

Until 16:00, no Avanti West Coast trains will run between London Euston and Milton Keynes Central.

An amended train service will run as follows:

  • 1 train per hour between Milton Keynes Central and Scotland
  • 1 train per hour between Milton Keynes Central and Manchester Piccadilly
  • 1 train per hour between Milton Keynes Central and Liverpool Lime Street
  • 1 train per hour between Rugby and Birmingham New Street
  • 1 train per hour between Crewe and Holyhead

Replacement bus details are not yet known, and will be published on www.nationalrail.co.uk when they are known.

London Northwestern Railway:

Until 16:00, no London Northwestern Railway trains will run between London Euston and Watford Junction.

An amended train service will run as follows:

  • 2 trains per hour will run in each direction between Birmingham New Street and Milton Keynes Central.
  • 1 train per hour will run in each direction between Crewe and Milton Keynes Central.
  • An hourly shuttle service will run between Milton Keynes Central and Watford Junction, calling at all stations.

Rail replacement bus services will run between both Milton Keynes Central and Bedford, connecting with trains to London St Pancras and between Watford Junction and Potters Bar, connecting with trains to London Kings Cross.

It is advised to travel on either Great Northern, Thameslink or East Midlands Railway services between Bedford and London St Pancras, and Great Northern or Thameslink services from Potters Bar to London Kings Cross.

A full service will resume on the London Overground Lioness line after 4pm.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
North West and Central Media Relations
Press Office
Network Rail
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk