West Coast main line reopens after successful Christmas rail upgrade near Stafford: One of two bridges being replaced on the West Coast main line near Stafford over Christmas

Tuesday 29 Dec 2015

West Coast main line reopens after successful Christmas rail upgrade near Stafford

Region & Route:
| National
| North West & Central

The West Coast main line near Stafford has reopened on time after Network Rail’s orange army completed four days of upgrade work to track and bridges over Christmas. 

While the majority of Britain was tucking into Christmas dinner and resting over the festive period, engineers were out in force to lay track as part of a £250m project to upgrade the West Coast main line – Europe’s busiest mixed-use railway – through Stafford.

Two bridges carrying the railway over local waterways were also replaced as part of Network Rail's Railway Upgrade Plan. 

The track work this Christmas is vital to help bring a new railway flyover into use at Easter 2016 which will remove a bottleneck on the main route between England and Scotland and provide passengers with a more reliable railway.

Mark Killick, area director for Network Rail, said: “This work is part of a £250m programme of rail investment to help improve performance and reliability of the West Coast main line. It was carefully planned and safely delivered to cause the least disruption to passengers, with work taking place on Christmas Day and Boxing Day when no trains would have run and over the Christmas bank holiday when fewer people use the railway.

“Our Railway Upgrade Plan is consistently delivering improvements and this Christmas has been no different with thousands of the orange army working across the network to maintain and upgrade the railway to meet the demands of the millions of passengers who travel by train every day.”   

Network Rail’s £250m Stafford Area Improvements Programme involves bringing into use the new railway flyover over the West Coast main line at Norton Bridge at Easter 2016 as well as linespeed and signalling upgrades between Stafford and Crewe which have already been delivered. All of the investment will provide the capability for more passenger and freight services to run on one of the busiest rail routes in Europe.

Steven Fisher, head of regional services at London Midland, said: “Travelling by train has never been more popular. Improving the network to add more capacity and reliability is essential to meet this growing demand. With fewer passengers travelling over the Christmas and New Year break this is the optimum time to carry out major works while minimising disruption to people’s journeys.”

The work is being delivered by the Staffordshire Alliance - a partnership of Atkins, Laing O’Rourke, Network Rail and VolkerRail.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk