Thursday 18 Sep 2025
Weeknight engineering work between Cambridge – Ely – King’s Lynn this autumn to keep trains running safely and reliably
- Region & Route:
- Eastern: Anglia
Network Rail will again be carrying out extra late-night engineering work on the Fen Line between Cambridge and King’s Lynn to improve the condition of the track, meaning that services north of Cambridge will finish earlier than usual on some weeknights in late September and October.
Following the driest spring in 50 years and prolonged dry spells this summer, the Fen Line is still being affected by the shrinkage of peat soil, which has caused the track to drop in places and become uneven. The ground will start to stabilise as more rain falls, but for now sections of track still need to be treated to help avoid speed restrictions that would cause significant disruption for passengers.
Engineers will use machines called tampers to lift the track, push ballast underneath and create a solid foundation so that trains can run smoothly. New ballast will also be dropped where it’s needed to help raise the level of the track.
Already this summer and early autumn, Network Rail has made the most of extra engineering hours on the Fen Line to treat about 9km of track and drop 600 tonnes of ballast. This is in addition to the 25,800 tonnes of ballast dropped on the route in the past two years to prepare for prolonged dry spells like the one this year.
Across the East Anglia railway in the last two months, engineers have treated around 55km of track and dropped 1,750 tonnes of ballast to help minimise the impact on passengers.
Simon Milburn, infrastructure director for Network Rail Anglia, said: “Thank you so much to passengers on the Fen Line – and across the region – for bearing with us this summer and autumn. Our teams are working really hard to limit the need for much more disruptive service changes by treating long stretches of affected track.”
Jenny Saunders, Customer Services Director for Govia Thameslink Railway which runs Great Northern and Thameslink trains, said: "I'm very sorry that some of our passengers will be affected by these engineering works. They are vital to ensure the continued safety and reliability of our services.”
As track work continues on the Fen Line, services will be affected as follows.
Between Monday 29 September and Thursday 2 October inclusive:
After approximately 23:00 buses will replace trains between Cambridge and Ely, with a shuttle train service operating between Ely and King’s Lynn.
For Great Northern on the affected evenings:
- The last direct northbound train from London King’s Cross to Ely and King’s Lynn will depart at 21:39
- The last direct train from King’s Lynn to London King’s Cross will depart at 21:42. Note, this is the last service that provides a connection to London.
- The last train from King’s Lynn at 22:42 will run as far as Ely. From there a replacement bus will run to Cambridge, but please note this will not arrive in time for an onward connection towards London.
- The last direct train from Ely to London King’s Cross will depart at 22:48. Buses will run to Cambridge after this time.
- The 22:09 service from London King’s Cross will terminate at Cambridge rather than Ely.
- The 22:39 and the following service from London King’s Cross – which is at 23:09 on Monday and Tuesday and at 23:07 on Wednesday and Thursday – will terminate at Cambridge rather than King’s Lynn. The last replacement bus from Cambridge will be extended up to King’s Lynn.
On Greater Anglia:
- The 22:40 Norwich to Cambridge service is replaced by a bus between Ely and Cambridge
Between Monday 6 October – Thursday 9 October inclusive, and between Monday 20 October – the early morning of Friday 24 October:
- On Great Northern services, buses will replace trains between Ely and King’s Lynn after 21:45
Notes to Editors
Vital weekend engineering works are also taking place around Ely Junction this October and November, with buses replacing trains. Read more
Passengers should check journeys before they travel at greatnorthernrail.com / greateranglia.co.uk / nationalrail.co.uk
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Richard Cooper
Communications manager
Network Rail
0330 8577 132
richard.cooper3@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk