WATCH: Storm damaged railway reopens to passengers after around the clock work to fix 33 washouts

Region & Route:
Wales & Western: Wales & Borders
| Wales & Western

Engineers have worked 24/7 to reopen the Cambrian Line between Shrewsbury and Newtown on the first weekend of April, following flood damage caused by Storm Franklin in February. 

The stretch of Cambrian Line has been closed to allow vital repairs to take place following extensive flood damage caused by Storm Franklin on Monday, 21 February. Initially, it was thought just 12 areas of ballast (the stones that hold the railway sleepers in place) had been washed away but further investigation revealed 33 severely impacted locations across a half-mile stretch of railway. 

The washouts happened after the River Severn flooded, with the water rising 3.9metres above the normal level - just 9cm lower than the highest ever recorded level. It took ten days for the river to fully recede before engineers could move in to repair the railway.  

Following just six weeks of 24/7 shifts, Network Rail engineers, working alongside contractors AmcoGiffen, have managed to restore the railway, ready for train services to resume on the first weekend of April. 

The extensive repair work has included the removal of 3,000 tonnes of debris, 4,000 tonnes of new ballast being laid, three tamping shifts to realign and level the track, 800 metres of double track replaced, new hedgerows planted, clearing of 11 culverts and installation of new fencing and telecoms cables.  

In March, Network Rail announced millions of pounds emergency funding to further protect this section of the line. Engineers are currently working on a resilience solution for this section of railway which will see rock armour installed along the embankment. Rock armour is a proven to work resilience method which prevents the stones from washing away during extreme weather, which means the railway can reopen in days, rather than weeks. 

Transport for Wales is planning to resume some passenger services on Saturday afternoon, following track testing in the morning. A full level of rail service is due to start back from Sunday 3 April. 

Bill Kelly, route director for Network Rail Wales & Borders said: "It’s fantastic to be able to fully reopen the Cambrian line for passengers, after the scenes of absolute devastation left in the wake of Storm Franklin. 

“I’d like to thank passengers, and the local community, who’ve shown incredible patience and support, throughout. I’d also like to pay tribute to everyone who’s worked so hard to repair the railway so quickly in such challenging conditions - it really has been an incredible effort.” 

Martyn Brennan, Transport for Wales Operations Director, said: "We would like to thank our customers for their patience while this essential work has taken place and we look forward to returning to a full service on the Cambrian Line from Sunday 3 April.” 

Claire Williams Partnership Development Officer from the Cambrian Railway Partnership said: "We are delighted to see that the vital link for connectivity to Shrewsbury and beyond on the Cambrian Line has been resurrected in good time and in readiness for the high demand of services over the Easter holidays. 

“We would like to thank our colleagues at Network Rail for their tremendous effort to reopen the line as soon as possible given the challenging conditions and devastation of the line outside Welshpool.” 

Other resilience work on the Cambrian Line in recent years includes raising Black Bridge, near Machynlleth, away from a flood zone. Before this innovative project was completed, the bridge had been closed 30 times in the last decade (ten times in 2020 alone) for emergency repairs caused by flood water. Since completion of the work in 2021, the railway at this location has not succumb to flooding or needed to be closed due to bad weather.  

Notes to Editors

Drone & time lapse footage, high-res images and footage showing rock armour installation on the Conwy Valley Line in 2020 (as reference for upcoming rock armour installation on the Cambrian Line) can be found here: https://we.tl/t-UFNBIezFDT 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Kathy Peart
Media relations manager
Network Rail
kathy.peart@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk