Update: Lewes to Seaford upgrade: Lewes signal box - picture Adrian Backshall

Thursday 7 Mar 2019

Update: Lewes to Seaford upgrade

Region & Route:
Southern

Paul Harwood, director of investment, South East: 

"Following discussions with our contractors over the past week, we’ve come to the conclusion that there was no longer confidence that the final commissioning of the signalling equipment from Lewes to Seaford could be completed over the 4-day closure of the railway.  We were not prepared to risk the lines not reopening for passengers on Monday morning and have therefore taken the very difficult decision to postpone that part of the work. 

"Unfortunately, when we learned of the risks to the final commissioning it was too late to reinstate a train service, so we are doing as much of the signalling and other planned work as possible over the 4-days, as well as bringing forward additional planned work to ensure we make best use of the closures and minimise future disruption for passengers. 

"We’d like to apologise to passengers for not delivering all the benefits of the upgrade over the closure as promised.  We’d also like to apologise to our Southern colleagues at Govia Thameslink Railway who have worked closely with us to plan these closures and who will be running the bus replacement service over the 4-days. 

"We will now work with our partners and local stakeholders to reschedule the final commissioning to a date when it will cause least disruption to passengers, business and the local tourism industry".

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Ross Boyle
Senior communications manager
Network Rail
07730 354 480
Ross.Boyle@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk