Update: Hastings to Tonbridge railway landslip: Whatlington landslip on Hastings-Tonbridge line

Wednesday 12 Mar 2014

Update: Hastings to Tonbridge railway landslip

Region & Route:
| Southern

Engineers continue to work to rebuild the damaged railway embankment at Whatlington, which has left train services unable to run between Battle and Robertsbridge since early February.

Network Rail had hoped that services could be restored along the full length of the Hastings line last week, however further movement of the landslip undermined the repair work that had been completed and means that additional strengthening work is now needed before trains can run safely.

Network Rail has bolstered its team with additional independent engineering expertise to investigate and determine the causes of the continued ground movement, which is affecting the substantial repairs put in place and preventing the line from reopening.

Whilst this detailed investigation is undertaken, the continuing ground movement around the embankment makes it difficult for Network Rail to accurately predict the work required and how soon this stretch of line can be bought safely back into use.

Fiona Taylor, Network Rail's route managing director for Kent, said: “This has been a very difficult time for everyone using this stretch of railway and we appreciate passengers’ patience while we do the work that is needed. Despite extensive surveying and expert work we were disappointed that the ground around the landslip moved again. This area is still not safe and we have to undertake more detailed in depth ground investigations to determine why this happened.

“We are putting everything into determining these causes and what works we have to do to make this stretch of line and the embankment safe for trains to run on.

“We know that passengers will be frustrated by this but we want to assure them that their safety is our upmost concern and we are doing everything we can to get to the bottom of this serious problem and put in place a safe and resilient embankment for the Hastings line. I’d like to extend my thanks once again to Southeastern and their passengers for continuing to bear with us while we complete what has become a real engineering challenge.”

The landslip at Whatlington is one of three significant landslips to have disrupted services on the Hastings line recently, with repairs already completed at Stonegate and Battle enabling trains to run along the line, with the exception of the section between Battle and Robertsbridge. Rail replacement bus services will continue to operate between these stations until further notice.

Notes to editors

There have been three serious embankment slips on the Hastings to Tonbridge line.
Embankment near Marley Lane level crossing, near Battle, slipped on January 30.
This resulted in the closure of the Battle/Robertsbridge section.
Embankment near Whatlington Viaduct, near Battle, slipped on February 3.
Embankment near Stonegate station slipped on February 9.
This resulted in the closure of the Wadhurst/Robertsbridge section.
Robertsbridge to Wadhurst reopened on Monday, March 3.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - South East route
020 3357 7969
southeastroutecomms@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk