Work to repair the damage caused by a derailed freight wagon on the Gospel Oak to Barking line (on Thursday 23 January) is progressing well and the timescale for completion of the work is expected to be confirmed next week.

More than two and a half miles of the route between Barking and South Tottenham was damaged in the incident. Network Rail’s engineers are almost half way through the programme of repairs having removed the damage and installed more than a mile of sleepers and top stone in preparation for re-railing next week.

The full programme of repairs includes replacing 39 pieces of rail, 5300 concrete sleepers, 900 wooden sleepers, removing and replacing 10,000 tonnes of ballast during the track replacement and replacing custom-timbers at ten bridges.

The line will remain part-suspended while the complex work programme takes place.

Ellie Burrows, Network Rail’s route director for Anglia said: “Our engineers are working as quickly as possible to reopen the line to minimise the disruption this incident is causing and work is progressing well.  I’d like to say sorry to our passengers and lineside neighbours and thank them for their patience while the work is ongoing.”

Just after 6am on Thursday 23 January, a freight wagon derailed between Leyton Midland Road and Walthamstow Queens Road on the Gospel Oak to Barking line which has caused extensive damage. An investigation into the cause of the incident is ongoing.

Travel Advice for Passengers

There is currently no London Overground service between Barking and South Tottenham. Passengers wishing to travel between Walthamstow Central and Barking are advised to continue to check the TfL Journey Planner before travelling. A rail replacement bus service has been provided between Walthamstow Central and Barking calling at Leyton Midland Road, Leytonstone High Road (Harrow Green), Wanstead Park and Woodgrange Park to allow passengers to complete their journey while repairs are underway.

Passengers can check before travelling by visiting tfl.gov.uk/plan-a-journey and https://www.nationalrail.co.uk for service updates.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Katie Mack
Media relations manager (Anglia route)
0330 8577 132
Katie.Mack@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk