TRU’s Baker Viaduct crosses the River Calder in Ravensthorpe: Ravensthorpe beam installation - River Calder

Wednesday 29 Jul 2026

TRU’s Baker Viaduct crosses the River Calder in Ravensthorpe

Region & Route:
Eastern

The newly built Baker Viaduct in Ravensthorpe now spans the River Calder with the penultimate pair of beams installed today (July 29), connecting the structural steelwork either side of the water.

The 350m long, 2,400-tonne viaduct now spans two waterways after crossing the historic Calder & Ribble Navigation Canal last year, and forms a pivotal part of TRU work at the programme’s Ravensthorpe site, which is one of the biggest civil engineering sites in the country.

The viaduct will be connected to a newly built grade-separated flyover to accommodate new rail alignments with four tracks, that allow direct services to overtake stopping services and reduce journey times across the route.

To facilitate the connection of the railway between the Viaduct and the Flyover, approximately 130,000m ³ of material was placed for earthwork structures like embankments and retaining walls in 2025 alone, with a similar volume expected to be placed throughout 2026.

In addition to the track realignment works across this stretch of railway, TRU are also building a brand-new Ravensthorpe station 200m west of its original location, to allow passengers in the future to access services to both Leeds and Wakefield.

 

Adam Bunce, Senior Project Manager for TRU, said:

“Baker Viaduct now spanning the River Calder is a significant milestone for TRU. This is an impressive feat of engineering and we’re really proud of everyone across our teams who have made it possible.

“When completed, Baker Viaduct will unlock faster, more reliable services for customers in the North. Work is also progressing well on the new Ravensthorpe station which, when reopened in 2028, will have a footbridge with lifts for step-free access, a new forecourt area and drop-off facilities, and new, extended island platforms so longer trains with more seats can stop there.

“Overhead line equipment (OLE) will also be installed throughout the area to power greener, electrified services.”

 

The TRU delivery team comprises of a number of contractor companies, including BAM Nuttall and Severfield, who played a key role in the work on Baker Viaduct.

 

Gareth Day, Projects Associate Director for Severfield, said:

“Today’s lift is the penultimate and thirty first installation lift of the Baker Viaduct and follows over sixty offline assembly lifts since we started on site last September.

Installing the final drop-in span is a very proud achievement for the Severfield Bridge team. 3D modelling of the structure started back in 2024, so the final lifts on site this week mark nearly two years of meticulous planning and engineering to successfully fabricate, deliver and install the 2,400t viaduct.”

 

To mark the occasion, TRU welcomed a number of representatives from Kirklees Council and West Yorkshire Combined Authority to have a first look at the new structure.

 

Cllr Eleanor Thomson, Weaver Network Board deputy chair, said: 

“The Transpennine Route Upgrade is a huge investment into our region.

“It was fantastic to see this feat of engineering slot into place – this kind of new infrastructure will lead to quicker, more reliable journeys and greater capacity for passenger and freight services, as well as boosting our economy.

“Better rail services will play a key role in our Weaver Network – a new, joined-up transport network for a better-connected West Yorkshire.”

Notes to Editors

The Transpennine Route Upgrade (TRU) is a multi-billion-pound railway programme that will transform journeys across the North, better connecting towns and cities like Manchester, Huddersfield, Leeds and York.

TRU fast facts

  • 25% of the route is now electrified, with electric train services now running between Manchester and Stalybridge, and York and Church Fenton
  • Once complete, TRU aims to halve the time lost to delays
  • There are currently 70 worksites across the 70-mile route
  • TRU will deliver:
    • The full electrification of the line
    • Double the amount of tracks in key locations, allowing fast trains to overtake stopping services
    • Implement digital signalling to increase speed and capacity
    • Improve all 23 stations on the route, supporting accessibility
  • TRU has over 5000 staff, with 85% coming from within 40 miles of the route – TRU will have created over 8000 jobs across the duration of the programme
  • TRU is expanding freight provision, opening 15 extra freight paths and widening tunnels so shipping containers can travel between ports on the east and west coasts via rail, removing over 1000 lorries a day from the busy roads across the Pennines

Key milestones to date

  • New station built at Mirfield
  • New station built at Morley
  • Introduction of a fully accessible platform 2 at Castleford station to support diverted services between York and Manchester
  • £100m upgrade of diversionary routes completed ahead of major works across the Transpennine Route, increasing railway resilience
  • Upgrade of Hope Valley line complete, with a second platform built at Dore & Totley, as well as 1km of additional track at Bamford to reduce bottlenecks

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Ewan Bayliss
Communications Executive
Network Rail
ewan.bayliss@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk