Transpennine Route Upgrade to deliver Christmas and New Year improvements between Leeds and York: TRU East OLE work-2

Thursday 27 Nov 2025

Transpennine Route Upgrade to deliver Christmas and New Year improvements between Leeds and York

Region & Route:
Eastern

Transpennine Route Upgrade (TRU) teams will take to the railway between Leeds and York over the Christmas period and throughout January to complete vital work, helping deliver faster, greener, more frequent services across the North.

Across the 32-day period spanning from Christmas Day until Sunday 25 January, a total of 45 engineering trains, 879 rail wagons, three large cranes and three tamping trains will be deployed.

Signalling and telecommunications upgrades will see a total of 70 new signals and accompanying infrastructure installed, tested and brought into use, helping create a more reliable and efficient railway. Before this takes place, eight level crossings will be closed, with most being replaced by safer alternative means for people to cross the line.

Tracks throughout the Church Fenton area will be remodelled, whilst platforms 3 and 4 at the station will be re-aligned and a new passing loop to enable direct services to overtake stopping ones will be installed. The overall line speed through this stretch of railway will be increased in the future as a result, meaning journey times will be reduced.

3km of track will be renewed along with eight switches and crossings which enable trains to change from one line to another, whilst overhead line equipment (OLE) installation will also continue, ready to power greener, electrified services.

 

Adam Sellers, TRU Senior Sponsor, said:

“Whilst we understand there is never an ideal time to carry out such essential work, this time of year has been specifically chosen as it is traditionally the quietest for rail passengers – we really appreciate the understanding of customers as we complete these major upgrades.

“The improvements will really take us a step closer to improved rail travel throughout the region and form a pivotal part of TRU plans across the wider route.”

 

Customers are being urged to plan their journeys ahead of time at nationalrail.co.uk or their train operator’s website if travelling during this period.

 

Chris Nutton, Major Projects & TRU Director at TransPennine Express, said:

“The investment by the TRU programme has already led to real progress in the Church Fenton area, with the line between York and Church Fenton now fully electrified. More improvements will be made during the Christmas period and into the new year, which will lead to a better and more reliable railway.

“For the duration of these works, TransPennine Express services between Leeds, York, and Selby will be impacted, with the level of impact changing during these 32 days of vital upgrade works. Diversionary routes will be used to keep people on trains where possible and rail replacement buses will be in operation as well.

“Because of the changing footprint of these works, we urge everyone to look ahead and check before travelling by visiting National Rail Enquiries.”

Notes to Editors

Thursday 25-Friday 26 December

No trains will run, in line with the annual Christmas shutdown of the UK rail network.

Saturday 27-Monday 29 December (11:30am)

No trains will run between Leeds-York/Selby, with rail replacement buses in operation.

No trains will run between Wakefield Kirkgate-York, as well as Selby-York.

Monday 29 December (11:30am)-Saturday 3 January

Trains will run between Leeds-Micklefield/Selby, serving local stations in between.

No trains will run between Leeds-York, and Wakefield Kirkgate-York, with rail replacement buses in operation.

Sunday 4 January-Sunday 25 January

Trains will run between Leeds and York, diverted via Castleford.

No trains will run between Micklefield-Church Fenton, with rail replacement buses in operation.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Ewan Bayliss
Communications Executive
Network Rail
ewan.bayliss@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk