Transpennine Route Upgrade prepares for major upgrades between Dewsbury and York: TRU Track Work-2

Tuesday 30 Sep 2025

Transpennine Route Upgrade prepares for major upgrades between Dewsbury and York

Region & Route:
Eastern

Customers are being urged to check before they travel as work between Dewsbury and York throughout October and November means there will be changes to services.

The closures of the railway are in place to facilitate essential work as part of the multi-billion-pound Transpennine Route Upgrade.

From Monday 6 October until Friday 24 October (excluding weekends), TRU teams will be undertaking work at Batley and Dewsbury stations to prepare for platform extension work that will see them become 150m and 200m long respectively. These platform extensions will allow longer trains to stop at the stations in the future, with more seats for customers. Bridge reconstructions will also take place on this section of railway.

Track and drainage renewal work will also be undertaken during this three-week period, which will allow faster, more reliable services to run.

Between Morley and Leeds, engineers will install foundations for overhead line equipment (OLE) masts. These masts will carry the electric wiring which will power greener, electrified trains across the North – 25% of the Transpennine route is now electrified following the introduction of electric services between York and Church Fenton in August.

 

Jonathan Hepton, project sponsor for TRU, said:

“These are crucial upgrades for the railway in West Yorkshire, but they will have a huge impact on the wider route as they are pivotal in enabling faster services with more capacity.

“Our teams will be working around the clock to deliver this safely and on time, following important milestone for the programme at Huddersfield station. We’d like to thank local businesses, residents and customers for their understanding as we complete these upgrades.”

 

TransPennine Express services between Huddersfield and Leeds will be diverted via Wakefield during this period, whilst local stations in between will be served by rail replacement buses.

 

Joe Munro, TRU Customer Lead at Northern, said:

“This next stage of work between Huddersfield, Dewsbury and Leeds is key to delivering an upgraded railway and unlocking benefits for our customers, not just at the impacted stations but across the route.

“Whilst this work takes place, trains will be unable to run through Dewsbury station. To keep customers on trains as much as possible, we will divert our Wigan to Leeds services via Bradford Interchange, whilst rail replacement services will connect Huddersfield and Halifax to Dewsbury and Leeds, as well as local stations in between.

“We would recommend that our customers who normally travel on this route to check before they travel at www.nationalrail.co.uk”

 

Chris Nutton, Major Projects & TRU Director at TransPennine Express, said:

“It’s exciting to see the progress being made to improve the railway’s performance and capacity in West Yorkshire, while the next steps are also being taken in the electrification of the route.

“Whilst these improvement works are carried out, we won’t be able to run trains on the line between Ravensthorpe and Leeds. To keep customers on trains as much as possible, we will divert trains between Huddersfield and Leeds via Wakefield, slightly increasing journey times. Rail replacement services will connect Huddersfield, Dewsbury, Leeds, and all local stations in between.

“Customers are advised to check before they travel using our digital channels and we’ll have extra staff on hand at key stations to help people get from A to B.”

 

Further work will also take place over six consecutive weekends this autumn on 4-5, 11-12, 18-19, 25-26 October, 1-2 and 8-9 November, between Leeds, York and Selby. This will include track renewals, signalling upgrades and installing foundations for new overhead line equipment. In addition, engineers will also install the new, fully accessible Barrowby Lane bridleway footbridge near Garforth, and carefully remove the historic cast iron arches at Crawshaw Woods bridge, ready for it to be refurbished.

To allow these upgrades to take place safely, trains between Leeds and York/Selby will be diverted via Castleford, with rail replacement buses serving local stations.

During the final three weekends - 25-26 October, 1-2 and 8-9 November - work will also take place just south of York to replace two sets of heavily used track points, which are crossed by more than 100 trains every day. This essential renewal will improve reliability for services arriving into York from Leeds. While this work is carried out, there will be no trains between Leeds and York, and rail replacement buses will operate throughout.

Customers are being encouraged to plan their journeys ahead of time at nationalrail.co.uk or their train operator’s website.

Notes to Editors

Ravensthorpe-Leeds works: weekdays 06/10 to 10/10, 13/10 to 17-10, 20/10 to 24/10

  • Preparation work at Dewsbury and Batley stations, to help facilitate platform extensions
  • Track & drainage renewals
  • OLE foundation installation
  • Weekday services impacted, weekend services unaffected

Neville Hill (Leeds)-Church Fenton works: weekends of 4-5, 11-12, 18-19, 25-26 October, 1-2, 8-9 November

  • Track renewals & signalling upgrades
  • OLE foundation installation
  • Installation of new, fully accessible Barrowby Lane bridleway footbridge
  • Removal of cast iron arches at Crawshaw Woods bridge
  • Weekend services impacted, weekday services unaffected

 

 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Ewan Bayliss
Communications Executive
Network Rail
ewan.bayliss@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk