Trains running as normal on North Cotswolds line after engineering work completed: N Cots line work Aug 2025 2

Tuesday 26 Aug 2025

Trains running as normal on North Cotswolds line after engineering work completed

Region & Route:
Wales & Western: Western

Trains began running again between Worcester Shrub Hill and Moreton-in-Marsh on bank holiday Monday morning after Network Rail completed engineering work.

 

Seven days of non-stop work took place on the North Cotswolds line to keep the railway running safely and smoothly.

2,000 yards of rail that had reached the end of its working life was replaced at three sites, two near Evesham and another at Honeybourne.

A new 500-yard walkway was built at Honeybourne station for train drivers who need to collect the “token” to use the relief lines.

Maintenance also took place inside the 900-yard-long Chipping Campden tunnel, built in 1853. Other tasks, such a clearing overgrown vegetation, were also completed.

Network Rail programme manager Jason Pankhurst said: 

“We’ve worked round the clock to complete this essential work to improve the railway.

“I'd like to thank passengers for their patience as we completed this work to improve the resilience and reliability of the network for years to come." 

GWR station manager for Oxford, Didcot and North Cotswolds area, Billy White, said:

“We’re very grateful to our customers from the North Cotswolds region for their patience while Network Rail completed these essential works over the last week.

“The works, which are part of ongoing maintenance to the railway’s infrastructure, help to ensure we can continue to provide consistent and reliable services for the community and those visiting the area by train.”

-ends-

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - James Crook
Senior Media Relations Manager
Network Rail
07732 644202
james.crook@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk