Passengers can travel as normal between Swindon and Bristol Parkway this morning after Network Rail completed work to reduce the impact of flooding on the railway in Chipping Sodbury.
Seven days of non-stop work took place in and around Chipping Sodbury tunnel in Gloucestershire to mitigate the impacts of flooding in the area and make the railway more resilient.
On the Bristol side of the tunnel, 200m of track has been raised by up to 20cm at the western end of the tunnel, whilst the rails and sleepers were lifted and additional ballast (track stone) laid and compacted. The overhead lines which provide power to trains were also adjusted in line with the higher track.
Drainage channels were inspected and cleared to allow more water to be collected and one of four pumps that remove water from the railway was replaced. Two pumps will be replaced later this year with the potential to install new pumps at the eastern end of the tunnel in the coming years.
This project was the latest in a wider scheme to ease the effect of flooding on the railway and in the surrounding area. Network Rail are working alongside the Environment Agency, South Gloucestershire Council, the Farming and Wildlife Advisory Group and Wessex Water to find long-term solutions.
Follow-up work will take place on Sunday 20 July, meaning the railway will be temporarily closed between Swindon and Bristol Parkway on this day, with trains diverted via Chippenham and Bath. For more information and to plan journeys, visit nationalrail.co.uk or GWR.com.
Network Rail project manager George Barratt said:
"I’d like to thank passengers for their patience as we completed this vital work to help mitigate the impacts of flooding on the railway, which will help us recover services more quickly in future and minimise delays.
“This is the latest piece of our ongoing programme to make the railway more resilient to the elements, and we will continue to work on long-term solutions with our partners.”
ENDS
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - James Crook
Senior Media Relations Manager
Network Rail
07732 644202
james.crook@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk