Train services resume between New Malden and Twickenham after four-day line closure for upgrades: Kingston Bridge viewed from above during the works

Wednesday 18 Feb 2026

Train services resume between New Malden and Twickenham after four-day line closure for upgrades

Region & Route:
Southern: Wessex
| Southern

Train services are running between New Malden and Twickenham in south west London again after Network Rail engineers carried out four days of improvements to the railway.

In Kingston, engineers replaced 25 pairs of wheel timbers, the long blocks that support the tracks, on Kingston River Bridge. The team also carried out general maintenance in the area to improve the reliability of services in south west London.

The new wheel timbers, made of Fibre-reinforced Foamed Urethane (FFU), will have a life span of up to 50 years meaning fewer closures will be needed for maintenance. These replaced the old wooden wheel timbers which had reached the end of their serviceable life.

With the line closed, engineers took the opportunity to complete a range of supporting maintenance work in the area. This includes carrying out maintenance to the signalling in Teddington after the completed Feltham and Wokingham Area Resignalling Programme.

Engineers also demolished redundant signalling equipment buildings at Strawberry Hill and Shepperton, and renewed the level crossing surface at Hampton. Together, this work will help to keep the railway safe and reliable for passengers.

Speaking on behalf of Network Rail and South Western Railway, George Murrell, Wessex Route Renewals Director, said: “We’d like to thank passengers for their patience while this work took place in south west London over the four-day line closure. Our teams worked around the clock to renew the railway and passengers will benefit from smoother and more reliable journeys.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Tom Moore
Communications Manager
Network Rail
07354531500
Thomas.Moore@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail