Track repairs under way at Stonehaven: Stonehaven pic1 141020

Friday 16 Oct 2020

Track repairs under way at Stonehaven

Region & Route:
Scotland’s Railway: Scotland

The latest stage in extensive recovery and reinstatement works has begun following the Stonehaven derailment on August 12.

Our engineers are now relaying over 500 metres of track following the recent completion of work to repair the bridge and embankment damaged in the accident.

Work will continue into November as our teams remove and replace the damaged track and relay 400 metres of telecoms cables.

Teams have worked day and night over the past few weeks to complete repairs to 70 metres of bridge parapets and remove the crane pad built over the Carron Water for the recovery of the carriages in September.

A considerable amount of engineering work is also being carried out to repair and extend drainage systems on the railway track and lineside embankments at the site.

The 06:38 ScotRail Aberdeen to Glasgow Queen Street service derailed on August 12 after striking a landslip with the devastating loss of three lives - driver Brett McCullough, conductor Donald Dinnie and passenger Christopher Stuchbury.

Alex Hynes, managing director of Scotland’s Railway, said: “This is a very complex and challenging recovery and repair operation and it will take time for our engineers to fully restore the track and other infrastructure.

“While we will reopen the line for customers as soon as possible, our focus throughout the recovery process has been on making sure we do all we can to learn from this terrible accident and try to prevent similar incidents happening in the future.”

ScotRail is operating a shuttle service between Aberdeen and Stonehaven and between Dundee and Montrose to keep customers in the north east moving. A replacement bus service also remains in place between Dundee and Stonehaven, and between Dundee and Aberdeen.

Cross-border operators are also running replacement buses between Aberdeen and Edinburgh, with more information available at https://www.nationalrail.co.uk/service_disruptions/253790.aspx

After the incident on August 12, Network Rail introduced a range of additional safety measures.

As an immediate precaution, hundreds of sites nationwide with higher-risk trackside slopes, similar to Stonehaven, were inspected.

These inspections were carried out by both in-house engineers and specialist contractors, supplemented by helicopter surveys.

Network Rail has also launched two taskforces, led by independent experts, as part of its long-term response to climate change and the challenge of maintaining its massive portfolio of earthworks (embankments and cuttings), many of which date from the Victorian era.

Dame Julia Slingo FRS, former chief scientist at the Met Office and a world-renowned expert in climatology, is leading a weather action taskforce with the objective of better equipping Network Rail to understand the risk of rainfall to its infrastructure, drawing on the latest scientific developments in monitoring, real-time observations and weather forecasting.

Lord Robert Mair CBE FREng FRS is spearheading an earthworks management taskforce to see how Network Rail can improve the management of its earthworks portfolio, looking at past incidents, latest technologies and innovations and best practice from across the globe.

Network Rail already invests heavily in earthworks and drainage, and spending has increased significantly in recent years from £550m between 2009 and 2014 to a budget of £1.3bn for the period between 2019 and 2024.

-ends-

Notes to Editors

Contact:

David.Boyce@networkrail.co.uk

Tel: 07810 556 249

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Scotland
0141 555 4109
mediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk