Temporary bridge will minimise Leven traffic disruption: Leven temporary bridge

Thursday 23 Mar 2023

Temporary bridge will minimise Leven traffic disruption

Region & Route:
Scotland’s Railway: Scotland

Work is underway to install a temporary bridge structure and build a road to enable the demolition and reconstruction of the A955 Leven Rail (Bawbee) bridge.

Construction of the new temporary crossing will support 18,000 vehicle movements per day during major work by Network Rail to demolish the old Bawbee bridge as part of the Levenmouth Rail Link project.

The A955 road bridge sits above the site of the new Leven station and, given its location, the reconstruction is being delivered as part of the wider Scottish-Government funded programme of railway works.

Work is now underway following planning approval from Fife Council for the diversion route during the eight-month road closure.

Up until now, traffic management has been in place to allow utility companies to move services off the structure to enable safe demolition without disruption to water, gas, electricity and telecoms.

Network Rail will replace the abutments and bridge deck of the weight-restricted 75-year-old road bridge which is suffering from significant deterioration and showing signs of chlorine contamination and corrosion.

As well as the temporary bridge and road, a new roundabout will be installed on South Street to support traffic movements during the project. The temporary bridge is due to open to traffic in early May.

Sean Clemie, Network Rail project manager for bridge works, said: “It’s great to get on site and start work on this part of the project.

“Chlorine contamination and corrosion means the bridge needs to be replaced sooner rather than later and it’s much easier and more cost effective to do this ahead of the new rail link opening.

“The installation of a temporary bridge will make a huge difference in minimising disruption in the area from the road closure.”

Councillor Colin Davidson, convener of Fife Council's Levenmouth Area Committee, said: “We are delighted to be working with the railway project to deliver the replacement Leven Rail Bridge, known locally as the Bawbee bridge.

“Given the location of the new Leven station, it makes sense to utilise the skills and expertise of the railway contractors to deliver this work efficiently both in terms of the road network and the rail link project.

“We appreciate the patience shown by the local community as contractors carried out preparatory work on the structure but, with the road set to close for an extended period, the installation of the temporary bridge will minimise the impact of the work on the community and support local businesses – particularly over the summer months.”

The diversion route will take traffic from the A955/B933 roundabout, through the swimming pool car park and across the River Leven via the temporary bridge. Traffic will then join the existing road network at the new roundabout on South Street (B932).

Upon completion of the works to Leven Bridge, anticipated to be in February 2024, the temporary diversion route will be removed and traffic will revert to the normal route over the new bridge. 

Notes to Editors

Notes to Editors

Key dates proposed for the work to replace the Leven (Bawbee) bridge are currently anticipated to be as follows: 

  • Start of temporary road construction- March 2023
  • Temporary road in use from – early May 2023
  • Leven Bridge renewal works – May – December 2023
  • Road reopened under Traffic management - December 2023
  • Removal of temporary road bridge  - January 2023
  • Road fully reopened – February 2024

 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk