Successful completion for Alloa engineering works: Alloa overhead line works 1

Monday 16 Apr 2018

Successful completion for Alloa engineering works

Region & Route:
Scotland’s Railway: Scotland

The Alloa line reopened this morning (Monday, April 16) following the successful completion of a four-week long, multi-million-pound upgrade project to prepare the line for electric trains.

Hundreds of engineers worked over 16,000 hours to install the overhead power equipment needed to introduce electric services on the route.

The work, which is part of a Scottish Government-funded programme to electrify lines throughout the central belt, started on Saturday, March 17.

Over the four weeks engineers worked from Stirling to Alloa along the six miles of the route, installing over 200 masts, and supporting cantilevers, and stringing overhead power lines.

The project is part of the wider programme to electrify the lines linking Stirling, Alloa and Dunblane to Glasgow and Edinburgh.

Once complete, in 2019, the electrification of Stirling-Dunblane-Alloa will mean:

  • Many services operated by electric class 385 trains, which will offer a better experience and reduce some journey times from Stirling to Glasgow and Edinburgh.
  • More seats on services between Alloa, Dunblane, Bridge of Allan, Stirling and Edinburgh.
  • Less noise and better air quality for those who live and work near the railway.

Humza Yousaf, Minister for Transport and the Islands, said: “I want to thank passengers for their cooperation and patience while alternative travel arrangements were in place. It will be welcome news that these works have been completed on time.

“Over this four week period Network Rail crews worked tirelessly to safely and successfully install over 200 masts and 14 kilometres of overhead wiring, taking us a step closer to electric services on the Stirling to Alloa route by December 2018.” 

Paul Reilly, Network Rail programme manager, said: “Electrification will transform travel across the central belt of Scotland and is part of our commitment to delivering the best railway Scotland has ever had.

“Our engineers worked around-the-clock to complete this complex programme as quickly as possible in what were, at times, challenging weather conditions.

“We understand the inconvenience these works cause to some passengers and residents and we appreciate the patience they have shown while we delivered this vital element of our electrification programme.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk