Wednesday 11 Feb 2026
Strong progress as East Coast Main Line engineering programme reaches halfway point
- Region & Route:
- Eastern
- | Eastern: East Coast
The midway point has been reached on a run of four weekends’ improvement work on the East Coast Main Line, with strong progress made so far and important digital signalling tests to come.
To date there has been track renewal at Finsbury Park, St Neots and Sandy and Offord, renewal of switches and crossings (also known as points, which guide trains safely from one line to another) at Hitchin and Woodwalton, upgrades to overhead line equipment between Sandy and St Neots and renewal of drainage at Stevenage, Biggleswade and Langford and platform upgrades at Alexandra Palace.
Work also took place to reprogramme the on-track balises (beacons) ready for upcoming testing as part of the East Coast Digital Programme (ECDP) – scheduled for 15 February and 21-22 February – with 101 test cases planned including train testing, speed restriction management and shunting.
A full system data update will also take place, as preparations continue towards digital signalling being introduced on the East Coast Main Line between Welwyn and Hitchin from later this year. Moving to in-cab signalling will enable more reliable, greener, and even safer journeys.
The work means that on 15 February* there will be no long-distance services between Peterborough and London, and no trains between:
- Potters Bar and St Neots/Letchworth Garden City
- Moorgate and Finsbury Park
- Stevenage and Hertford North
Rail replacement buses will operate between Peterborough and Bedford. Thameslink and Great Northern will have various rail replacement bus services in place, with some bus routes connecting up with train services on the Midland Main Line for journeys to and from central London.
On 21-22 February** there will be no trains between Potters Bar and Peterborough/Royston, and no trains between Hertford North and Stevenage. Long distance operators will run amended services with rail replacement bus services in place between Peterborough and Bedford. Thameslink and Great Northern will have various rail replacement bus services in place, with some bus routes connecting with train services on the Midland Main Line for journeys to and from central London.
Ricky Barsby, Network Rail’s head of access integration, ECDP, said:
“I’d like to thank passengers for their patience during the closures over the last two weekends. A huge amount has been done by our teams to deliver a wide range of vital work to upkeep and upgrade the network, and to prepare for further digital signalling testing.
“We have a further three days of route closures this month, as critical testing takes place ahead of the introduction of in-cab digital signalling later this year. This will be an exciting change to the way we operate the network, enabling more reliable services for the thousands of passengers who depend on the East Coast Main Line. We thank passengers for their understanding over the three upcoming affected days.”
A spokesperson for the train operating companies added:
“We’re grateful for passengers’ patience for the past two weekends of work. We’ll continue to work hard to keep passengers moving while this essential work takes place. Rail replacement bus services and revised timetables will help people reach their destinations, and our teams will be on hand to support customers. We encourage everyone to check their journey before travelling.”
Click here to learn more about ECDP.
Notes to Editors
The upcoming weekends of ECDP testing will involve a Grand Central Class 180 unit and Great Northern Class 717.
*On Sunday 15 February:
- LNER will have an amended service north of Peterborough, with rail replacement coaches operating between Peterborough and Bedford to connect customers with services to/from London St Pancras. Passengers travelling between the north and London are strongly advised to use LNER services and provided rail replacement services to and from Peterborough and London and avoid travelling via Sheffield, Derby or Chesterfield due to extremely high passenger numbers on the Midland Main Line.
- Hull Trains will run a reduced timetable between Hull and London St Pancras. Trains will not call at Beverley, Cottingham, Doncaster, Retford, Grantham or Stevenage.
- Lumo will have an amended service between Glasgow Queen Street/Edinburgh and Newcastle only.
- No Grand Central trains between London King’s Cross and Bradford Interchange/Sunderland.
- Great Northern and Thameslink trains will not run between Potters Bar and Letchworth Garden City/St Neots or between Hertford North and Stevenage. There will also be no trains between Moorgate and Finsbury Park. Rail replacement buses will operate between:
- Hitchin and Letchworth Garden City
- Bedford and St Neots
- Hitchin and St Neots
- Luton Airport Parkway and Stevenage via Hitchin
- St Albans and Stevenage via Hatfield
- Hertford North and Stevenage
- Potters Bar and Hitchin
**On 21-22 February:
- LNER will have an amended service north of Peterborough, with rail replacement coaches operating between Peterborough and Bedford to connect customers with services to/from London St Pancras. Passengers travelling between the north and London are strongly advised to use LNER services and provided rail replacement services to and from Peterborough and London and avoid travelling via Sheffield, Derby or Chesterfield due to extremely high passenger numbers on the Midland Main Line.
- Hull Trains will run a reduced timetable between Hull and London St Pancras. Trains will not call at Beverley, Cottingham, Doncaster, Retford, Grantham or Stevenage.
- Lumo will run an amended and reduced service between Newcastle and Edinburgh only.
- There will be no Grand Central trains between Sunderland/Bradford Interchange and London King’s Cross.
- There will be no Great Northern/Thameslink trains between Potters Bar and Royston or Peterborough, as well as between Hertford North and Stevenage. Replacement buses will run between:
- Hitchin and Royston/Peterborough
- Bedford and Peterborough via St Neots
- Luton Airport Parkway and Stevenage via Hitchin
- St Albans City and Stevenage via Hatfield
- Hertford North and Stevenage
- Potters Bar and Hitchin
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Gareth Dennison
Media relations manager, Eastern region
Network Rail
07561 874858
gareth.dennison@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk