Thursday 26 Nov 2026
Southeastern rail services continue to run over Christmas and New Year. Customers advised to plan ahead due to Lewisham signalling upgrades
- Region & Route:
- Southern
- | Southern: Kent
- Much of the Southeastern network will be open this Christmas period but an adjusted timetable will be in operation
- Engineers will be commissioning a £90m signalling upgrade at Lewisham
- Extra services will run after midnight on New Year’s Eve to allow revellers to get home
Southeastern services will be running over the Christmas and New Year period, but timetable changes and engineering work may affect journeys. Please plan ahead and check before travelling.
The Christmas period sees a significant reduction in London-bound commuters (travellers who exit London terminals before 10am). With fewer passengers over the festive period, an adjusted timetable will run on weekdays from Monday 21 December. Services on Christmas Eve shut down by approximately 10pm, while no services run on Christmas Day and Boxing Day.
Southeastern are running additional services out of central London until approximately 2:30am on New Year’s Day. When service resumes later that morning, a Sunday service will be in operation. Normal services will resume on Monday 4 January, when the network traditionally sees a return to regular commuting levels.
From 25–28 December, no services will run from London Charing Cross, Waterloo East or London Cannon Street for essential signalling upgrades in the Lewisham area. A limited service will run to and from London Bridge, with other services diverted to and from London Victoria.
These lines will close again after the last extra train has completed its journey following the New Year’s Eve celebrations, fully reopening for the start of services on Monday 4 January 2027.
What work is being carried out?
During the first closure, South Eastern Railway’s engineering teams will complete the £90m Lewisham signalling upgrade, activating new trackside equipment and train-control systems. At Christmas, the teams will install two signalling structures to keep drivers’ views of signals clear, connect the railway’s power supply, then clear sites and remove equipment. Over two years, more than 200km of signalling has been installed, telecoms and power cables, four new signals and 10 new equipment-case suites to connect to signalling equipment. During the second closure, the team will make adjustments and remove redundant railway equipment.
The new signalling will improve reliability and resilience across south east London and into Kent, reducing faults and delays. In recent years, failures involving the types of equipment being replaced, including track circuits, relay-based interlocking and associated lineside cabling, have caused many thousands of minutes of delay.
Simpler maintenance and fault-finding will help engineers resolve problems. Layout changes will enable higher train speeds on affected sections, while upgraded automatic route-setting will improve service management. The main benefits are fewer infrastructure-related delays and a more reliable, resilient signalling system that is easier to maintain and support in the long term.
This work forms part of a wider signalling upgrade across south London with upgrades to the signalling at Herne Hill, Nunhead and Battersea areas continuing into next year. Work to complete this significant signalling upgrade on the network will take place in the 2027 Christmas period.
Scott Brightwell, South Eastern Railway’s Director of Safety and Performance, said:
“We’re committed to keeping customers moving over the festive season, but ask them to plan ahead to avoid surprises at the station.
“Engineers will work throughout the period, including Christmas Day, Boxing Day and New Year’s Day, to deliver vital signalling improvements at a key junction on our railway.
“The upgrade will make services through Lewisham more resilient, reducing delays caused by signalling faults in south London in 2027.”
Summary of services during the 2026 Christmas period
|
DAY |
SERVICE OPERATING |
|
|
Monday 21 to Wednesday 23 December 2026 |
An adjusted service level will operate, with some additional services at the busiest times. |
|
|
Christmas Eve Thursday 24 December 2026 |
An adjusted service level will operate, with some additional services at the busiest times. No passenger trains will operate after approx. 22:00 |
|
|
Christmas Day Friday 25 December 2026 |
No Southeastern services will operate. |
|
|
Boxing Day Saturday 26 December 2026 |
No Southeastern services will operate. |
|
|
Sunday 27 December 2026 |
A normal Sunday service level will operate with some additional trains at the busiest times. Engineering work will take place on the following routes: Charing Cross / Cannon Street to Bexleyheath / Sidcup / Grove Park / Hayes. |
|
|
Bank Holiday Monday 28 December 2026 |
A Saturday service level will operate. Engineering work will take place on the following routes: Charing Cross / Cannon Street to Bexleyheath / Sidcup / Grove Park / Hayes. |
|
|
Tuesday 29 and Wednesday 30 December 2026 |
An adjusted service level will operate, with some additional services at the busiest times. |
|
|
New Year’s Eve Thursday 31 December 2026 |
An adjusted service level will operate, with some additional services. Additional early morning services from Midnight for Central London revellers. |
|
|
New Year’s Day Friday 1 January 2027 |
A Sunday service level will operate. Engineering work will take place on the following routes: Charing Cross / Cannon Street to Sidcup / Petts Wood, Gillingham to Faversham / Sheerness, Otford to Ashford. |
|
|
Saturday 2 January 2027 |
A normal Saturday service level will operate. Engineering work will take place on the following routes: Charing Cross / Cannon Street to Sidcup / Petts Wood, Headcorn to Ashford, Sittingbourne to Herne Bay / Dover. |
|
|
Sunday 3 January 2027 |
A normal Sunday service level will operate. Engineering work will take place on the following routes: Charing Cross / Cannon Street to Sidcup / Petts Wood, Headcorn to Ashford, Sittingbourne to Herne Bay / Dover. |
|
|
Monday 4 January 2027 |
Normal services resume |
|
Notes to Editors
Amended services due to engineering works
Sunday 27 December
Paddock Wood Line: Services between London Charing Cross and Ramsgate / Dover Priory via Tonbridge will run to and from London Victoria instead.
Hastings Line: Services between London Charing Cross and Hastings will use London Victoria instead.
Maidstone East Line: Services between London Charing Cross and Maidstone East will depart from London Victoria instead, with an extra stop at Bromley South.
Bexleyheath Line: All trains on this line will be replaced by buses.
Woolwich Line: Services between London Cannon Street and Dartford via Woolwich will not operate. London Cannon Street–Slade Green services via Greenwich will run between London Bridge and Gravesend instead.
Grove Park Line: Services between London Charing Cross and Sevenoaks will not operate.
Services to and from London Victoria will call at stations between Petts Wood and Sevenoaks.
Sidcup Line: Services will run between Sidcup and Dartford only.
Hayes Line: All trains on this line will be replaced by buses.
Bromley North Line: All trains on this line will be replaced by buses.
Bank Holiday Monday (28 December):
Paddock Wood Line: Services between London Charing Cross and Ramsgate / Dover Priory via Tonbridge will run to and from London Victoria instead.
Hastings Line: Services that normally run only between London Charing Cross and Tunbridge Wells will not operate. London Charing Cross–Hastings services will run to and from London Victoria instead.
Maidstone East line: Services between London Charing Cross and Maidstone East will not operate.
Bexleyheath Line: All trains on the Bexleyheath Line will be replaced by buses.
Woolwich Line: Services between London Cannon Street and Dartford via Woolwich will not operate. London Cannon Street–Slade Green services via Greenwich will run between London Bridge and Gravesend instead.
Grove Park Line: Services between London Charing Cross and Sevenoaks, and between London Cannon Street and Orpington, will not operate.
Services to and from London Victoria will call at stations between Petts Wood and Sevenoaks.
Sidcup Line: Services will run between Sidcup and Dartford only.
Hayes Line: All trains on the Hayes Line will be replaced by buses.
Bromley South Line: London Victoria–Orpington services will run every 30 minutes and extend to and from Sevenoaks.
Bromley North Line: All trains on the Bromley North Line will be replaced by buses.
Other travel options:
- Travel at no extra cost on London Underground between Victoria, Charing Cross, Embankment, Waterloo, Southwark, London Bridge, Cannon Street, Blackfriars and Elephant & Castle
- Travel at no extra cost on the Docklands Light Railway between Lewisham and Greenwich
Timetable changes 1-3 January 2027
Paddock Wood Line: Services between London Charing Cross and Ramsgate / Dover Priory via Tonbridge will run to and from London Victoria instead.
On Friday 1 January, London Victoria–Ramsgate services will run only between London Victoria and Ashford International due to additional engineering work.
On Sunday 3 January, these services will run hourly via Maidstone East due to additional engineering work between Headcorn and Ashford International.
Hastings Line: Services between London Charing Cross and Hastings will use London Victoria instead.
On Saturday 2 January, the usual stopping services between London Charing Cross and Tunbridge Wells will not run.
Maidstone East line: Services between London Charing Cross and Maidstone East will not operate.
Bexleyheath Line: Services between London Cannon Street and Slade Green via Bexleyheath, and between London Charing Cross and Dartford, will not operate.
Services between London Victoria and Gravesend via Bexleyheath will run as usual.
Woolwich Line: Services between London Cannon Street and Slade Green via Greenwich will run between London Bridge and Dartford instead.
Grove Park Line: Services between London Charing Cross and Sevenoaks will not operate.
Services to and from London Victoria will call at stations between Petts Wood and Sevenoaks.
Sidcup Line: Services will run between Sidcup and Dartford only.
Hayes Line: Services will run to and from London Victoria every 30 minutes.
Bromley North Line: All trains on this line will be replaced by buses.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Tom Moore
Communications Manager
Network Rail
07354531500
Thomas.Moore@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk