Six months of electrification work delivered in 18 days on Fife railway: Muriespot -  Fife electrification project - October 2026

Thursday 29 Oct 2026

Six months of electrification work delivered in 18 days on Fife railway

Region & Route:
Scotland’s Railway: Scotland

Engineering work that could have taken up to six months of weekend shutdowns has been completed in just 18 days as part of the electrification of the railway in Fife.

Network Rail closed sections of the Fife circle between 10-27 October so engineers could work around the clock to prepare the route for overhead electric wires that will power new battery-electric trains.

During the 18-day closure, bridges at Bennochy Road in Kirkcaldy, Muriespot near Coaltown of Balgonie and Main Street in Thornton were demolished and work began to rebuild them at a greater height, creating space for the overhead electric wires. A total of 29 concrete beams were installed as part of the new bridge structures.

Teams also installed more than 200 foundations and 20 steel structures for the overhead wires, as well as four new masts on the Leven line.

Signalling equipment, which helps control the safe movement of trains, was upgraded around Burntisland, with 26 pieces of older equipment replaced. Further upgrades were also completed between North Queensferry and Kirkcaldy.

More than 209,000 square metres of vegetation was cleared from beside the railway and modifications made to the platforms at Cardenden Station.

Completing the work during one 18-day closure meant it could be done in a fraction of the time. Using weekend closures alone, the same amount of work could have taken up to six months.

The work is part of a £311.5m Scottish Government investment to electrify 118km of railway in Fife and introduce battery-electric trains. The new trains will reduce the railway’s reliance on diesel and are expected to provide more reliable, comfortable and sustainable journeys.

Michael McArthur, project manager at Network Rail Scotland, said: “It’s been an incredibly busy 18 days, and our teams have done a fantastic job delivering such a huge amount of work, including working through Storm Boelo and other spells of difficult weather.

“Having the railway closed gave us the chance to do several big jobs at once rather than returning over a series of weekends. That has helped us make real progress towards bringing battery-electric trains to Fife.

“We know closing the railway has meant disruption for passengers and communities, and we’re grateful for their patience while this work has taken place.

“There’s a lot more still to do, but what’s been achieved over these 18 days brings us another step closer to a quieter, greener and more reliable railway for Fife.”

More information about the Fife electrification project is available on the Scotland’s Railway website.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail Press Office - Natasha Richardson
Senior Media Relations Manager
Network Rail
07701274676
natasha.richardson@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk