Scotland’s Railway powering on with feeder station upgrades: Feeder Station 1

Tuesday 8 Nov 2022

Scotland’s Railway powering on with feeder station upgrades

Region & Route:
Scotland’s Railway: Scotland

Scotland’s Railway is working to deliver the next in a series of enhancements to the power supply supporting our electrified railway network.

As part of a £120m Scottish Government investment to add resilience and capacity into the network, Network Rail and SPL engineers are introducing a new modular feeder station and upgrading a key track section cabinet (which helps regulate the power supply) near Glasgow Central station.

This is a crucial part of work to upgrade and reconfigure our power supplies to support the increased demand that will be created by the introduction of electric trains on the lines between Glasgow and Barrhead and East Kilbride.

Alice Wilson, scheme project manager for traction power at Network Rail, said: “The £120m Scottish Government investment to upgrade the electric power supply into the rail network is key to helping us meet our target to decarbonise Scotland’s Railway by 2035.

“This work will power the cleaner, greener electric trains on the Glasgow- Barrhead and East Kilbride lines in the coming years. This directly supports decarbonising passenger services on Scotland’s Railway by 2035 and delivering the modal shift required for Scotland to reach Net Zero.

“Working on Glasgow’s electrified rail network is always challenging but our industry partners have worked with us to plan, design and deliver the work in a way that reduces risk, minimises disruption and helps us to move forward with our plans to decarbonise the network.”

The installation of the substation will be delivered without disruption to passenger and freight services.


Work on the £120m traction power investment to upgrade is well underway with Ferguslie feeder station in Paisley being installed in July 2022. It will enter into service in early 2023.

Phase one of the investment will see six new feeder stations and nine upgrades to traction power infrastructure locations on the railway across the central belt, Scottish Borders and Fife.

Upgrades to the power supply network will be ongoing until 2026. Investment will increase the resilience of the existing network, the new connections to the national grid via the feeder stations will increase the overall capability of the 25kV electrified network.

Upgrading the power supply network will enable the introduction of electric trains on services to East Kilbride and Barrhead, on the Borders line and across Fife but will also support increased traffic on existing routes such as the East Coast Mainline.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk