Residents and passengers thanked as bridge renewal in Haverfordwest is completed: Milford Road railway bridge (2)

Monday 18 Feb 2019

Residents and passengers thanked as bridge renewal in Haverfordwest is completed

Region & Route:
Wales & Western: Wales & Borders
| Wales & Western

The A4076 at Milford Road railway bridge in Haverfordwest has re-opened and train services between Whitland and Milford Haven have resumed as normal, following the successful replacement of Milford Road railway bridge this weekend.

Over the weekend, Network Rail teams worked around the clock to demolish and remove the existing railway bridge deck - which carries the South Wales Main Line. Engineers then installed a new, more resilient steel structure which includes a concrete collision beam to provide extra resilience, as part of Network Rail’s Railway Upgrade Plan to improve the reliability of the railway in West Wales.

Rhys Howells, scheme project manager for Network Rail Wales and Borders, said: “We would like to thank the local community and rail passengers for bearing with us whilst we replaced Milford Road railway bridge.

“The previous bridge deck was nearing the end of its serviceable life and has now been replaced with a more resilient structure which will help to keep the railway in West Wales running reliably.”

These essential works form part of a £4.25m upgrade project to replace two bridges in Merlins Bridge, which also included the successful replacement of Pembroke Road railway bridge in January. 

Finishing works, which include masonary repairs, track tamping and construction of retaining walls, continue at both Pembroke Road and Milford Road railway bridges.

To ensure all these works can be completed safely and effectively single lane traffic management will be in operation on Pembroke Road at the bridge and the A4076, at Milford Road bridge, intermittently overnight until the end of March 2019.

For more information visit www.networkrail.co.uk/Merlins-Bridge.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Bryony Parry
Media Relations Manager
07734 649220
Bryony.Parry@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk