Reminder: vital embankment work means 13 consecutive days of rail replacement on the East Suffolk Line

Region & Route:
Eastern: Anglia

From this Saturday 25 March to Thursday 6 April, Network Rail will be working to stabilise and widen a mile-long embankment on the railway to the north of Martlesham, on the East Suffolk Line.

There will be no direct trains between Ipswich and Lowestoft throughout these 13 consecutive days, with rail replacement buses operating between Ipswich and Saxmundham.

Passengers are being advised to check before they travel and to look out for further changes to services on 30 March and 1 April, when there is planned industrial action.

Saxmundham station’s car park will be closed during the works because it is being used for rail replacement buses.

The engineering work is needed because the top of the embankment is slipping away. This means that important signalling equipment and signage is gradually falling down the bank, potentially affecting the future safe and reliable running of the line.

There is also currently no walkway for railway workers along the embankment, meaning that access to carry out essential maintenance is severely limited. The widening work will provide enough space for a new walkway.

Finally, the improvements need to be completed before a mile of worn-out track on top of the embankment can be replaced.

Network Rail will be back to carry out this track work between 16-25 August, when buses will replace trains for 10 consecutive days. Renewing worn-out track is essential to minimising faults and delays.

Mark Walker, Network Rail Anglia route infrastructure engineer, said: “I’m really sorry that passengers will face extended stretches of bus replacement. However, the major work on this steep, high embankment is vital to help keep trains on time and avoid sudden disruption or closures. We are building an East Suffolk Line that is fit for the future.”

Jamie Burles, Greater Anglia managing director, said: “This improvement work will help ensure we can continue to operate a punctual train service along the East Suffolk Line. Our new trains are already providing a very good service on the route and this engineering work will help ensure we can continue to deliver high standards of performance on a consistent basis and provide a more comfortable journey for passengers.

“A rail replacement bus service will run between Ipswich and Saxmundham between 25 March and 6 April so customers can complete their journeys. We would advise everyone to check before they travel and allow more time for their journey. We would like to thank customers for their patience while this work is carried out.”

In addition to the embankment stabilisation and widening, engineers will carry out the main work to renew the surfaces of two level crossings in Woodbridge on 25 and 26 March. This follows the completion of upgrades on three other nearby crossings, making them easier and safer to use for pedestrians, cyclists and drivers.

Notes to Editors

Full size bicycles and e-scooters cannot be carried on rail replacement buses.

During these works and the upcoming strike action, passengers are advised to check before they travel at greateranglia.co.uk or nationalrail.co.uk

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Richard Cooper
Communications manager
Network Rail
richard.cooper3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail